How Alberta's Prompt Payment and Construction Lien Act works: 28-day and 7-day payment clocks, notices of dispute, adjudication, 10% holdback, 60-day lien registration, lien bonds and public works payment bonds.
Education only / verify at source / not legal advice. This guide explains Alberta's Prompt Payment and Construction Lien Act (the "PPCLA") as it reads in the Alberta King's Printer office consolidation current as of April 1, 2025, together with the Prompt Payment and Adjudication Regulation (current as of November 26, 2025) and, for Government of Alberta projects, the Public Works Act and Public Works Regulation (current as of September 17, 2026). Every rule cited comes from a public source retrieved on November 16, 2026 (PT), listed at the end. King's Printer consolidations are for convenience; the official statutes and regulations control. Global Guarantors publishes industry education. We aren't a surety, broker, insurer, government agency, Nominating Authority or law firm. The statute, the regulations, your contract, your bond wording and your own lawyer's advice control.
Start here: Surety 101: three parties, one written promise · Contract surety hub · Lien bonds and vacating liens in Canada
Alberta rebuilt its construction payment law in 2022. On August 29, 2022 the old Builders' Lien Act became the Prompt Payment and Construction Lien Act and gained three things it did not have: payment deadlines that run from a "proper invoice," written notices a payer must give if it will not pay, and fast, binding adjudication through government-designated Nominating Authorities. The lien and holdback rules stayed, with longer registration periods and a path for releasing holdback on large projects.
Government of Alberta projects are different. Since April 1, 2025, new provincial construction contracts have had their own prompt payment and adjudication rules in the Public Works Act. Those projects are outside the PPCLA, so unpaid trades have no lien and rely on the Crown's claim process and the payment bond.
For the surety market, the Alberta regime changes how quickly money moves down a bonded project, produces binding adjudicator orders that can land on a bonded contractor within weeks, keeps a 10% holdback and a land lien that can be removed by posting a lien bond, and leaves payment bonds as the main security on provincial public works.
The PPCLA is the old Builders' Lien Act, RSA 2000, c B-7, renamed and extended by the Builders' Lien (Prompt Payment) Amendment Act, 2020, which added Part 3 (prompt payment) and Part 5 (dispute adjudication) and changed lien and holdback periods. Alberta's prompt payment page and fact sheets give August 29, 2022 as the start date.
Transition. Contracts entered into on or after commencement "must conform to the new provisions"; earlier contracts stay under the former provisions "until expired, terminated or amended in order to conform," subject to the regulations (s. 74). Regulation s. 37 gave longer pre-commencement contracts two years to be amended; Alberta's page puts the compliance date at August 29, 2024.
Later amendments. Two rounds matter for anyone reading older commentary:
The PPCLA is built around an improvement: anything constructed, erected, built, placed, dug or drilled on or in land, other than things neither affixed to it nor intended to become part of it (s. 1(d)). "Work" includes services (s. 1(p)), and an equipment renter is deemed to perform a service while its equipment is on or near the site (s. 6(4)). The contractor contracts with the owner; a subcontractor is anyone else contracted under a contract, other than labourers and pure suppliers or service providers, who still have lien rights under section 6 (s. 1(b), (n)).
Exclusions that matter for bonding:
Municipal, school, health and other public owners that are not the Crown in right of Alberta are not carved out by name. Whether a project is a "public work" under the Public Works Act depends on who the contracting party is; confirm it before relying on, or ruling out, a lien.
Everything in Part 3 runs off the proper invoice: a written bill or request for payment for work or materials on an improvement that contains the contractor's name and business address; the invoice date and the period of the work; information identifying the authority (written, verbal or otherwise) for the work; a description of it; the amount requested and payment terms broken down for the work; the name, title and contact information of the person to be paid; a statement that the invoice "is intended to constitute a proper invoice"; and any prescribed information, plus other contract requirements (s. 32.1(1)).
The owner's deadline runs from receipt of the proper invoice. Lower-tier deadlines run mainly from receipt of payment, with a backstop counted from the date the proper invoice was given to the owner.
| Payment (PPCLA section) | Deadline | Notice to withhold |
|---|---|---|
| Owner to contractor (s. 32.2) | No later than 28 days after receiving the proper invoice | Notice of dispute no later than 14 days after receiving it |
| Contractor to subcontractor, owner has paid (s. 32.3(1)–(2)) | No later than 7 days after the contractor receives payment | Notice of non-payment by the s. 32.3(7) date |
| Contractor to subcontractor, owner has not paid (s. 32.3(4)) | No later than 35 days after the contractor gave the proper invoice to the owner | Within 7 days after the owner's notice of dispute, or before day 35 (s. 32.3(5), (7)) |
| Subcontractor to its subcontractor (s. 32.5) | 7 days after receiving payment; if unpaid, day 42 after the proper invoice was given to the owner | Within 7 days after the contractor's notice, or before day 42 (s. 32.5(8)) |
Paid in, paid down. A contractor paid in full must pay each subcontractor whose work was in the invoice within 7 days; on part payment, it passes down what the owner paid for each subcontractor's work, and where the shortfall is tied to particular subcontractors' work, the others are paid and the money for the disputed work is shared proportionately (s. 32.3(1)–(3)). Section 32.5 repeats the pattern one tier down and, by section 32.5(11), further down.
When the owner does not pay. If the owner does not pay on time, the contractor must still pay its subcontractors for their invoiced work no later than 35 days after giving the proper invoice to the owner, to the extent it was not paid (s. 32.3(4)). It avoids that duty for a subcontractor only by giving, on time, a notice of non-payment in the prescribed form stating that and the amount, an undertaking to refer the matter to adjudication within 21 days, and a copy of any owner's notice of dispute (s. 32.3(5)). Once the owner pays, the 7-day pass-through applies (s. 32.3(8)). Between subcontractors the backstop is day 42 (s. 32.5(4)–(5)), and a subcontractor short because the owner did not pay need not give the undertaking (s. 32.5(6)(b)). Subcontractors can ask when the proper invoice went to the owner (s. 32.5(10)).
Part 3 counts in "days"; see "What counts as a day" below.
An owner that disputes a proper invoice may refuse to pay all or part of it if, no later than 14 days after receiving it, it gives a notice of dispute in the prescribed form and manner, "specifying the amount of the proper invoice that is not being paid and detailing all the reasons for non-payment" (s. 32.2(2)). The undisputed balance stays payable by day 28 (s. 32.2(3)). Withholding under section 32.2 depends on a timely notice, and a notice that does not detail "all" the reasons may itself be disputed.
A contractor that receives a notice of dispute must tell its subcontractors "without delay," and a subcontractor that receives a notice of non-payment must do the same down the chain (s. 32.4). A contractor that disputes a subcontractor's entitlement for its own reasons, such as defects or back-charges, must give its own notice of non-payment with the amount and all reasons by the section 32.3(7) deadline (s. 32.3(6)); section 32.5(7) gives the same right one tier down.
Forms and service. The 2022 order in council that renamed the forms regulation as the Prompt Payment and Construction Lien Forms Regulation set out a notice of dispute (Form 1) and four notices of non-payment (Forms 2 to 5). That regulation has been amended since, so use the current forms from King's Printer. Unless the contract says otherwise, notices are delivered "by service at the relevant party's regular place of business" (Regulation s. 31).
Interest "begins to accrue in accordance with the prescribed rates on any amounts included in a proper invoice that are unpaid and due" (s. 32.6). The rate is the contract rate or, if none, the current rate under the Judgment Interest Regulation (Alta Reg 215/2011) (Regulation s. 4). Check the current rate. Part 3 does not reduce any duty to pay wages (s. 32.7).
Part 5 lets the Minister designate Nominating Authorities to qualify and appoint adjudicators, run training and keep a public registry (s. 33.2). Alberta's prompt payment page names two: ARCANA (AB) and ADACC (Alberta Dispute Adjudication for Construction Contracts). The ADR Institute of Alberta says ARCANA (AB) became a Nominating Authority effective April 19, 2023; its 2025–2026 annual report records 50 adjudications, up from 26 the year before. ADACC's site says Service Alberta designated it to administer adjudications and certify adjudicators.
Adjudicators need at least 10 years of relevant construction-sector experience and a certificate lasting up to three years (Regulation s. 7). Parties may name a Nominating Authority in their contract (Regulation s. 21), but a term that names the adjudicator in advance "is of no force or effect" (Regulation s. 20(3)).
Under Regulation s. 19, a party may refer disputes about valuation of services or materials, including approved, unapproved and proposed change orders; payment; disputes under a notice of non-payment; payment of holdback (the major or minor lien fund); and any other matter the parties agree to. Adjudication is between contracting parties (s. 33.4(1)), so a sub-subcontractor adjudicates against the party that hired it, not the owner.
An adjudication may not be commenced if the notice of adjudication is given more than 30 days after the date of final payment under the contract or subcontract, unless the parties agree otherwise (s. 33.4(2)). That date is the earlier of actual complete payment and the day complete payment is required under Part 3, and it ignores holdback and payment for post-substantial-performance work (s. 33.4(3)–(4)).
| Step | Deadline | Regulation |
|---|---|---|
| Notice of adjudication to the other party, copy to the Nominating Authority the same day | Before the 30-day final-payment cut-off | s. 20; Act s. 33.4(2) |
| Parties report an agreed adjudicator; authority appoints | Within 4 calendar days; appointment within 7 calendar days (after the 4-day window if no agreed name) | s. 22 |
| Claimant sends adjudicator the notice, contract and documents | Within 5 days of appointment | s. 23 |
| Response | Within 12 calendar days of receiving the claimant's documents | s. 24(2) |
| Determination and order | Within 30 days of the adjudicator receiving the claimant's documents, or as extended under s. 25(3) | ss. 25(3), 26(1) |
| Certified copy to the parties | Within 7 days after the determination | s. 26(3) |
The adjudicator may research independently, inspect the site and consult construction professionals (Regulation s. 25(1)). Related adjudications can be consolidated, but not once more than 5 calendar days have passed since any adjudicator said it had everything needed to decide (Regulation s. 30).
The Regulation defines "calendar day" as "a day other than a Saturday or a holiday as defined in the Interpretation Act" (Regulation s. 1(1)(b)), and the Interpretation Act counts every Sunday as a holiday (s. 28(1)(x)). That definition is stated for the Regulation, which uses "calendar days" for some steps (ss. 22, 24(2), 25(3), 30) and plain "days" for others (ss. 23, 26). The Act's Part 3 says "days" without defining them; under the Interpretation Act, a deadline falling on a holiday moves to the next non-holiday (s. 22(1)). The adjudicator may extend "one or more times, any deadline in the adjudication process to a maximum of 10 calendar days" (Regulation s. 25(3)). Diarize the earliest reading.
Cost. The Regulation sets no fees. Each Nominating Authority must publish its own fee schedule, and costs are split equally unless the adjudicator directs otherwise (Regulation s. 13). ARCANA (AB)'s prompt payment page cautions that its services "are not free," that fees are often borne first by the applicant, and that it "does not provide enforcement services." Verify current fees with the Nominating Authority.
Binding effect. A determination (s. 33.6(4)) binds the parties unless the court directs otherwise, an arbitrator under the Arbitration Act has made an award on the matter, or the parties settle by a written agreement made after the determination (s. 33.6(5); Regulation s. 1(2)). Apart from judicial review, a court or arbitrator may still decide the merits later (s. 33.6(6)). The adjudicator can order payment within a set time and allow the other party to stop providing services or materials if that time expires (Regulation s. 26(2)).
Registration. The clerk of the Court of King's Bench must register an adjudicator's order as a court order if it is submitted not less than 30 days after the parties received it and no court order, arbitration, award or written settlement intervenes (s. 33.61(1)). The outer limit is generally two years after the notice of determination (s. 33.61(3)). If a registered order requires payment to a contractor or subcontractor, that party's related duty to pay its own subcontractor is deferred while the order is being enforced (s. 33.61(5)).
Judicial review. An application must be filed and served within 30 days of the notice of determination and, since the 2024 amendments, "does not stay the determination ... unless the court directs otherwise" (s. 33.7). The grounds are listed in Regulation s. 34 and include bias, fraud, an unqualified adjudicator and a matter outside section 19.
Court in parallel. A later lawsuit on the same dispute can run alongside the adjudication unless the court directs otherwise, and a court decision on the merits ends the adjudication (s. 33.4(5)–(6)). The lien clock does not pause for adjudication.
An owner liable on a contract under which a lien may arise must, when paying, retain 10% of the value of the work actually done and materials actually furnished for 60 days from the date of the certificate of substantial performance or, if none is issued, the date of completion (s. 18(1)). The period is 90 days for improvements to an oil or gas well or well site (s. 18(1.1)) and for improvements primarily related to concrete (s. 18(1.2)).
That retained amount, plus unpaid contract money above it that the owner has not paid in good faith while no lien was registered, is the major lien fund (s. 1(h)). While a lien is registered, the owner must also hold back any unpaid balance above the 10% (s. 18(2)). If a contractor or subcontractor defaults, the major lien fund cannot, as against a lienholder, be applied to completion or any purpose other than satisfying liens (s. 18(6)).
Substantial performance. A contract is substantially performed when the work, or a substantial part, is ready for use or in use and the rest can be completed or corrected for no more than 3% of the first $500,000 of the price, 2% of the next $500,000 and 1% of the balance (s. 2). A certificate of substantial performance must be posted or provided electronically within 3 days (s. 20). After it issues, liens for earlier work charge the major lien fund and liens for later work charge a separate 10% minor lien fund (ss. 23–24); if 60 days (or 90) pass with no lien registered, the holdback duty is reduced accordingly (s. 21); and money paid after the certificate is held in trust for those who supplied the certified work (s. 22).
Section 24.1 requires an owner to pay out holdback during the project if the contract provides for a completion schedule longer than one year with annual payment of accrued holdback, or for phased payment specified in the contract; the contract price when signed exceeds the prescribed amount, which the Regulation sets at $10,000,000 (Regulation s. 2(2)); and on the payment date no liens are filed or all have been satisfied, discharged or otherwise provided for. If the contract does not specify phases, payment is annual (Regulation s. 2(1)). Our Ontario holdback explainer covers Ontario's differently structured release rules.
A person who does work on, or furnishes material for, an improvement for an owner, contractor or subcontractor has a lien on the owner's estate or interest in the land for the unpaid price (s. 6(1)). The lien arises when the work begins or the first material is furnished (s. 10). It is registered at the land titles office by filing a statement of lien, verified by affidavit, in the prescribed form (s. 34), and no lien may be registered unless the claim, or joined claims, total $700 or more (s. 35(3)).
| Lien for (s. 41) | General deadline | Oil or gas well or site; concrete |
|---|---|---|
| Materials, services or wages | 60 days from the last supply, completion of the services or work, or abandonment | 90 days |
| Contractor or subcontractor (other cases) | 60 days from completion or abandonment of the contract or subcontract | 90 days |
Fixing something later does not extend the window (s. 41(5)), and an unregistered lien that misses it "ceases to exist" (s. 42). For concrete, the Regulation adds that the 90-day lien period "does not apply to entities that install or use ready-mix concrete" (Regulation s. 36).
A registered lien ends unless, within 180 days, the claimant sues and registers a certificate of lis pendens (s. 43(1)), and an owner can shorten that with a notice to commence an action, after which the lienholder has 30 days (s. 45(1)).
Section 48(1) lets the court, on application, order a lien's registration removed from title where security is given or payment is made into court for the amount of the claim, the maximum the lien can properly attach to under sections 18(3)–(4) or 23(3)–(4), or a lesser amount the court sets, plus costs; where the relevant lien fund has been paid out; or on any other ground the court considers proper.
Money paid in or security given "stands in place of the land," is subject to the claimant's claim, and does not change the holdback the owner must keep (s. 48(2)). The lien survives as a charge against the security even if the claimant later misses the lis pendens or 180-day steps (s. 44). The paying side can also serve a notice to prove lien; the lienholder must then file an affidavit with detailed particulars within 15 days or lose the lien, unless the court extends the time (s. 48(3)–(5)).
The Act says "security," not "bond." In practice it is often a lien bond from a surety, in a form and amount the court accepts, underwritten with the principal and indemnitors behind it. Our lien bonds hub, linked under Start here, compares Alberta's section 48 with Ontario and BC.
Because the PPCLA does not apply to a "public work" under the Public Works Act except as that Act provides (PPCLA s. 1.1(1.1)), unpaid trades on Government of Alberta projects have no PPCLA lien. The Public Works Act binds the Crown (s. 1.2). Contracts entered into on or after the coming into force of its new provisions are governed by them (s. 14.6(2)), and Bill 30's amending section 3 was proclaimed in force on April 1, 2025.
Where the surety comes in. The Public Works Act defines "surety" as "a person who guarantees to the Crown the payment of creditors" (s. 15(0.1)). Thirty days after written notice to the contractor and the surety, the Crown may pay a claimant what it considers proper and deduct it from money owing to the contractor or from security deposited (s. 15(1)). If that is not enough, the surety must, to the extent of the security, pay the Crown on demand, and as against the Crown the payment is "final and binding" on the contractor and the surety (s. 15(2)–(3)). Contractors must, where practicable, post on site section 14 and any labour and material payment bond given to the Minister (s. 17(1)), and a bond's existence and particulars are public information (s. 17(2)).
The PPCLA does not require bonds; owners do, through tenders and contracts. On Alberta private work the usual Canadian forms are explained in our CCDC 221 and 222 guide, and the 2024 labour and material payment bond is summarized in our CCDC 222 wording card.
Prompt payment does not replace the payment bond. An adjudicator's order against a failed contractor is only as good as its balance sheet, and a lien only as good as the holdback and the land. A labour and material payment bond does not depend on either, and on a provincial public work it may be the main security an unpaid subcontractor has. Coverage, amount and notice depend on the bond wording; Canadian payment bonds commonly limit claimants to those contracting with the principal or with its subcontractors, and set written-notice and suit deadlines. Our subcontractor payment bond claim guide explains the usual structure.
Practical intersections:
This is our editorial view, not a description of how any surety prices or underwrites. Questions a reader might ask about a contractor with significant Alberta work:
A dated, high-level comparison. Use our Ontario and BC prompt payment page, our guide to the federal Act and the official sources for detail.
| Regime (status) | Payment clock | Adjudication |
|---|---|---|
| Alberta PPCLA (in force August 29, 2022; 2024 amendments in force April 1, 2025) | Owner 28 days, notice of dispute by day 14; contractor 7 days after payment, backstop day 35 | ARCANA (AB) or ADACC |
| Alberta Public Works Act (government contracts on or after April 1, 2025) | Crown 28 days; contractor 35 and subcontractor 42 days from their own invoices | Same authorities; $500,000 cap |
| Ontario Construction Act (October 1, 2019; further amendments January 1, 2026) | Owner 28 days | ODACC |
| Federal Act, federal real property (December 9, 2023) | Crown 28 days, excluding Saturdays, holidays and December 24 to January 1; Alberta is a designated province | CanDACC |
| BC Construction Prompt Payment Act (assented November 27, 2025; Parts 1 to 6 not in force as of November 10, 2026) | Not yet operative | Not yet operative |
Non-Alberta rows: ODACC, Justice Laws (including SOR/2023-269 s. 3) and BC Laws, opened November 16, 2026. Because SOR/2023-270 designates Alberta, the federal Act stops applying to subcontractors on federal projects here, while parts of it still govern the federal Crown and the prime contractor.
For a contractor or subcontractor on an Alberta job
For an owner or project team
For a surety, broker or claims professional
When did Alberta's prompt payment rules start? August 29, 2022, for new contracts; longer older contracts had to comply by August 29, 2024.
How long does an Alberta owner have to pay? 28 days after receiving a proper invoice, unless it gives a notice of dispute within 14 days for the amount it will not pay. The undisputed amount is still due by day 28.
Does a general contractor have to pay subcontractors if the owner has not paid? Generally yes, by day 35 after giving the proper invoice to the owner, unless it gives a notice of non-payment, undertakes to refer the matter to adjudication within 21 days and copies any owner's notice of dispute.
Who appoints adjudicators in Alberta? Nominating Authorities designated by the Minister, currently ARCANA (AB) and ADACC. The adjudicator must decide within 30 days of receiving the claimant's documents, subject to extensions under Regulation s. 25(3).
How long do I have to register a lien? Generally 60 days from completion, last supply or abandonment, or 90 days for oil and gas well work and concrete work. The claim must be at least $700.
Can I lien a Government of Alberta project? No PPCLA lien is available on a public work under the Public Works Act. Unpaid parties use that Act's notice of claim, adjudication up to $500,000, and any labour and material payment bond.
All sources below were retrieved on November 16, 2026 (PT). Dates in parentheses are the dates or currency statements those documents bear.
Educational explainer only. This page describes Alberta's construction prompt payment, adjudication, holdback and lien rules as the official consolidations and government pages read on November 16, 2026 (PT). It is not a claims-filing or lien-registration service, a substitute for the official statutes, regulations, forms, contract or bond, or legal advice. Global Guarantors is not a surety, broker, insurer, Nominating Authority or law firm. If a deadline, a notice, an adjudication, a lien or a bond claim matters to a decision, open the current official text, read the contract and the bond, and, where needed, take advice from a lawyer licensed in Alberta.