BC’s Construction Prompt Payment Act: Royal Assent Nov 27, 2025, still not in force as of Nov 5, 2026 — payment clocks, adjudication and surety watch-outs.
Education only / verify at source / not legal advice. This guide explains British Columbia’s Construction Prompt Payment Act, SBC 2025, c. 24, using the Bill 20 text on BC Laws, the Province’s Ministry of Infrastructure page, BC’s Builders Lien Act, Ontario’s Construction Act and ODACC materials, and Alberta’s public prompt-payment pages. Global Guarantors publishes industry education. We aren’t a surety, broker, insurer or law firm, and we don’t publish premiums. As of November 5, 2026 (PT), the BC Act is not in force. Confirm in-force status on BC Laws and the Province’s prompt payment page (Sources 1 and 3) before relying on any clock on this page. The current statute, your contract, your bond forms and your own lawyer’s advice control.
Start here: Surety 101: three parties, one written promise · Surety glossary · Surety vs insurance + indemnity
British Columbia passed a construction prompt-payment and adjudication statute in late 2025. It has not proclaimed it. Until the Lieutenant Governor in Council brings the Act into force by regulation, existing contracts, the Builders Lien Act holdback rules and ordinary dispute processes continue to govern how money moves on BC projects.
That status matters for brokers and sureties who write labour-and-material payment bonds and performance bonds on BC work. Faster statutory payment clocks and short adjudication windows — once live — can change when unpaid trades escalate a dispute. They do not rewrite bond conditions. This page is the deep dive that sits beside our shorter Ontario-and-BC briefing: treat that page as the series hub, and this page as the BC companion with dated callouts.
Status callout (November 5, 2026 PT): BC Laws still marks Parts 1–5 and Part 6 sections 47–51 as “Not in force.” The Province’s plain-language page (last updated August 20, 2026) still says the Act “is not yet in force.” No commencement regulation was found on a November 5 check. Re-check BC Laws and gov.bc.ca on publish morning; If any operative Part is proclaimed or a commencement regulation appears before publication on November 9, HOLD this draft; do not publish until all “not in force” language, clocks, transition and BLA statements have been rewritten against the proclaimed text.
British Columbia’s statute is the Construction Prompt Payment Act, SBC 2025, c. 24. It began life as Bill 20 in the First Session of the 43rd Parliament. BC Laws records assent on November 27, 2025.
The complete statute view on BC Laws is the cleanest status check: Parts 1–5 (sections 1–46) and Part 6 sections 47–51 are marked “Not in force.” Sections 52–58 list consequential amendments to the Builders Lien Act and the Strata Property Act. Section 59 is the commencement rule: the Act comes into force by regulation of the Lieutenant Governor in Council.
Responsibility sits with the Ministry of Infrastructure (the Province notes the file was developed under the Ministry of Attorney General). The Province’s public page — last updated August 20, 2026 — summarises the future regime in everyday terms: proper invoices, payment deadlines, adjudication, and implementation work still ahead. It states plainly that the Act “received Royal Assent on November 27, 2025, but is not yet in force,” and that regulations and an adjudication authority still need to land.
On May 26, 2026 the Province opened engagement on a Discussion Paper. Written submissions closed July 7, 2026. The news release lists the topics industry was asked about: how broadly the Act should apply; whether to implement all at once or in phases; delivery and business-day rules; interest rates; adjudicator qualifications, training and fees; standardized forms; and other implementation supports. As of the August 20, 2026 page update, the ministry said it was reviewing that feedback. A November 5, 2026 check found no public commencement regulation.
Until proclamation, existing contract payment terms and the current Builders Lien Act continue to apply. Do not calendar BC statutory prompt-payment clocks on live projects as if they were already law.
The clocks below come from Bill 20’s text. They are future rules. They do not run today.
| Clock (Bill 20) | Plain meaning | Section cue |
|---|---|---|
| Owner pay | Owner pays the contractor within 28 days after the invoice date of a proper invoice | s. 9(1)(a) |
| Downstream pay | A person further down the chain pays included subcontractors by the earlier of 7 days after receiving payment or that person’s calculated payment date | s. 9(1)(b) |
| Calculated payment date | 28 days plus 7 × the person’s contract position after the invoice date (owner = 0, contractor = 1, first-tier sub = 2, and so on) | s. 9(2), s. 2 |
| Invoice-form objection | An invoice given as a proper invoice is deemed proper unless, within 7 days after the invoice date, the owner gives written notice of what is wrong and how to fix it | s. 7(2) |
| Owner notice of non-payment | Owner must give a written notice of non-payment (amount and reasons) within 14 days after the invoice date if relying on s. 11 | s. 11(2)(b)(i) |

The Province’s plain-language page matches that design: 28 days owner to contractor after a proper invoice; 7 days downstream after receipt; 7 days to object to invoice form; 14 days for non-payment or partial-payment notice.
Two design points matter for underwriters who already know Ontario.
First, BC’s downstream rule is not only “seven days after you get paid.” It also uses a calculated payment date that walks down the pyramid by sevens. That backstop can matter when money never arrives from above.
Second, Bill 20 voids contract clauses that try to opt out of the Act or its remedies (s. 47(2)). Once the Act is in force for a contract, parties cannot contract out of the statutory scheme.
Partial payments have their own rules in section 10: early partial receipts can trigger rateable downstream payments. Interest on late statutory payments accrues at the higher of a prescribed rate and any contract rate (s. 15). The prescribed rate itself will come from regulations that do not yet exist.
Section 7 sets out what a proper invoice must contain: contractor name and address; invoice date; the period, milestone or other basis the invoice covers; contract or authorization identifiers; a description of the services or materials; the amount payable and payment terms; payment instructions; and any prescribed information, plus contractual requirements that are not void under section 6.
Section 6 is worth a separate read. Section 6(1) says that a provision making the giving of a proper invoice conditional on “the certification of a payment certifier or the approval of the owner is void.” Section 6(2) preserves certification or approval after the invoice is given, and testing or commissioning provisions.
The deeming rule in section 7(2) is the operational pressure point. If the owner stays silent for seven days after the invoice date, an invoice given as a proper invoice is deemed proper even if it was formally incomplete. The owner can still dispute amounts through a timely notice of non-payment. Deeming targets form and content objections, not every payment dispute.
Section 5 requires monthly proper invoices unless the contract sets a different period or a milestone basis. Section 8 allows revisions if the owner agrees in advance and the invoice date does not change.
For brokers educating clients before force: invoice hygiene will matter more once the clocks start. Owners who calendar intake carefully, and contractors who can show what was delivered and when, will be in a better position than parties who treat invoices as informal progress emails.

Section 11 is the non-payment gate. A person is not required to pay a statutory amount if they give the other person a written notice that specifies the amount and the reasons. If the reason is prior non-payment higher in the chain, the notice must also include a copy of any upstream notice of non-payment and an undertaking to refer that prior non-payment to adjudication within 21 days after the notice is given (s. 11(1)(b)).
Timing differs by tier. An owner’s notice is due 14 days after the invoice date. A contractor or subcontractor’s notice is due by the earlier of seven days after receiving a notice of non-payment or their calculated payment date (s. 11(2)(b)).
Once a disputed amount is later paid, the Act restarts a seven-day pay-through clock for that amount (s. 11(3)).
Section 13 ties this to holdback: a requirement to pay under Part 3 is subject to a required holdback under the Builders Lien Act, and retention of that holdback can be stated as a reason for non-payment. Section 14 keeps employment contracts and wages outside the Act.
Adjudication is Bill 20’s fast interim process for listed payment-related disputes. It is designed to keep cash moving while parties keep later court or arbitration rights.
Section 16 lists adjudicable matters, including failure to give a proper invoice; whether an invoice is proper; failure to make a Part 3 payment; a notice of non-payment (including holdback issues under s. 13); valuation of services or materials; whether a payment is required under the contract (including change-order questions); matters the parties agree to; and prescribed matters.
A party starts adjudication by giving a notice under section 18. Section 19 sets a 90-day outer limit after completion, abandonment or termination of the owner–contractor contract, or — for a subcontract — the earliest of prime-contract end, subcontract completion certification under the Builders Lien Act, or last supply under the subcontract.
Parties may select a consenting adjudicator, or ask the adjudication authority to appoint one (appointment within seven days of request). A contract clause that pre-names an adjudicator is void (s. 23(5)). The referring party must deliver the contract and supporting records within five days after the adjudicator consents (s. 25).
Subject to limited extensions, the adjudicator must issue a written determination with summary reasons within 30 days after receiving the section 25 records (s. 30). A late determination is void. The determination binds until a court or arbitration finally decides the dispute, or the parties agree otherwise (s. 31).
A party ordered to pay must pay within 15 days after the determination is issued (s. 34). If they do not, the unpaid party may suspend further work and recover reasonable suspension and resumption costs (s. 35). A certified determination may be filed with the Supreme Court within two years and enforced as a judgment (s. 36). Judicial review is limited and must be started within 35 days (ss. 39–40).
Part 5 lets the minister designate an adjudication authority to train and qualify adjudicators, keep a public registry, appoint adjudicators and provide administrative support. Until someone is designated, the minister may perform those functions. As of November 5, 2026, the Province still describes selection of an adjudication authority as work ahead — another reason the Act is not yet live.
Prompt payment and holdback are related but not the same tool. Bill 20 does not replace BC’s holdback statute. Section 13 makes Part 3 payments subject to required BLA holdbacks. Section 37 does the same for amounts ordered in a determination.
Under the current Builders Lien Act, SBC 1997, c. 45 (current to October 27, 2026 on BC Laws):
Those are today’s rules. They are the rules that apply while the Prompt Payment Act remains unproclaimed.
Bill 20’s consequential amendments (ss. 52–57) would, once in force with the Act:
Bill 20 does not enact an Ontario-style mandatory annual release of accrued basic holdback. Secondary firm commentary has noted that difference; the primary confirmation is the Bill itself: holdback changes are targeted BLA amendments, not a new annual-release Part. For Ontario’s annual-release regime, use our separate holdback page rather than this BC deep dive.

| Feature | British Columbia (passed; not in force) | Live comparator (Ontario / Alberta) |
|---|---|---|
| Statute | Construction Prompt Payment Act, SBC 2025, c. 24 | ON: Construction Act, R.S.O. 1990, c. C.30 · AB: Prompt Payment and Construction Lien Act (PPCLA) |
| In force? | No as of Nov 5, 2026 (PT) | ON: prompt payment/adjudication since Oct 1, 2019; further amendments Jan 1, 2026 · AB: Aug 29, 2022 (new contracts; transition for older) |
| Owner pay clock | 28 days from invoice date (Bill 20 s. 9) | ON: 28 days from receipt of proper invoice (s. 6.4) · AB: 28 calendar days of receiving a proper invoice (alberta.ca) |
| Downstream | 7 days after receipt or calculated date | ON: 7 days after receiving payment (ss. 6.5–6.6) · AB: 7 calendar days after receiving payment from the owner |
| Invoice deeming / deficiency | 7 days (s. 7(2)) | ON: 7-day deeming in s. 6.1(2) (Jan 1, 2026) · AB: proper-invoice content list on alberta.ca; follow the Act/regs for deeming detail |
| Owner non-payment notice | 14 days after invoice date | ON: 14 days after receiving proper invoice (s. 6.4(2)) · AB: 14 calendar days of receiving the invoice |
| Adjudication authority | To be designated; not yet selected | ON: ODACC · AB: ARCANA and ADACC |
| Annual holdback release | Not adopted in Bill 20 | ON: mandatory annual release package in force Jan 1, 2026 · AB: annual/phased release on large multi-year private projects (alberta.ca: ≥ $10M and > 12 months) |
Ontario’s January 1, 2026 refinements are live law. ODACC’s prompt-payment page notes that further Construction Act amendments came into force on that date and points readers to the Act for proper-invoice detail. Our Canada prompt payment: Ontario & BC briefing walks the Ontario clocks in more detail; our Ontario construction holdback page covers annual release. Use those pages for Ontario; do not treat this BC page as an Ontario manual.
Alberta’s public pages confirm PPCLA force on August 29, 2022 for new construction contracts, with later compliance deadlines for some existing contracts, and separate Public Works Act treatment for many government projects. Alberta is a useful comparison for “live Western prompt payment,” not a template for BC’s unproclaimed text.
Federal construction sits outside all three provincial regimes: see Canada's Federal Prompt Payment for Construction Work Act for the federal 28-day clock and CanDACC adjudication.
Education-level watch-outs only. No claim playbooks.
Once BC’s clocks and adjudication are live, unpaid subcontractors and suppliers may reach a written interim determination faster than they would through court or arbitration alone. That may change when a trade looks at a labour-and-material payment bond — especially on CCDC-style private work or public contracts that require a payment bond. It does not change the bond’s notice conditions, suit limitation, claimant definition or penal sum. Point clients to the bond form, the contract and counsel.
Disclosure of payment bonds remains a separate Canadian issue. Our Valard v. Bird payment-bond disclosure page covers the Supreme Court of Canada’s payment-bond disclosure duty. The Bill 20 text reviewed here does not address or displace that duty; keep the two analyses separate.
For the standard Canadian labour-and-material form itself, CCDC 222 remains the common Canadian labour-and-material specimen (see Related reading for the field card). We do not host licensed CCDC PDFs.
Prompt-payment defaults and work suspensions after unpaid determinations can be early distress signals on a bonded contract. A performance-bond surety still underwrites and investigates under the performance bond and indemnity agreement, not under the Prompt Payment Act. Faster cash-flow fights may compress the calendar around default notices and takeover decisions. Keep payment-dispute chronology in the underwriting and claims file without improvising statutory strategy from an education page.
Because Bill 20 leaves BLA holdbacks in place (and only shortens the holdback period once proclaimed), lien rights and lien-bond vacating practice remain central in BC. Our lien bonds in Canada page covers security to cancel a claim of lien under BLA section 24 and related Canadian routes. Do not conflate a prompt-payment adjudication determination with a lien, a holdback release or a bond claim.
Owners and contractors preparing for force should review tender security and P&P packages the same way they already do for other Canadian jurisdictions with prompt payment. Our bid bonds in Canada (CCDC 220) page and contract surety primer sit upstream of payment-bond claims. Prompt-payment readiness is mostly about invoice and notice systems, not about changing bid-bond percentages.
Section 50 is blunt: the Act will not apply to a contract entered into before section 50 comes into force, or to a subcontract that relates to such a contract. That is a bright line for transition — once force dates are known.
Section 51 allows regulations under the application section to phase the Act in by sector or by public/private classes. The May–July 2026 consultation expressly asked whether implementation should be all-at-once or phased. Until regulations land, nobody can say which BC project types go first.
Practical drafting notes for the pre-force period (still not legal advice):
Explicit non-goals for this section: no sample adjudication notices, no “how to beat adjudication,” no invented payment-dispute → bond-notice matrices, and no premiums, ratings or anonymized loss figures.
Before the Act is in force
When regulations and a force date appear
Surety desk habits (education only)
Is British Columbia’s Construction Prompt Payment Act in force today? No. As of November 5, 2026 (PT), BC Laws still marks the operative Parts as not in force, and the Province’s page (last updated August 20, 2026) states the Act is not yet in force. It comes into force only by Lieutenant Governor in Council regulation.
What are the headline payment deadlines once the Act is live? Bill 20 provides for owner payment within 28 days after the proper invoice’s invoice date, downstream payment by the earlier of seven days after receiving payment or a calculated payment date, a seven-day window to object to invoice form, and a fourteen-day owner notice of non-payment. None of those clocks run until the Act is proclaimed for the relevant contract.
Did BC adopt Ontario’s mandatory annual holdback release? No. Bill 20 keeps prompt payment subject to Builders Lien Act holdbacks and makes targeted BLA amendments (including a shorter holdback period and abolition of Shimco liens against the holdback) that also await force. It does not create Ontario’s annual-release scheme.
How does adjudication interact with a labour-and-material payment bond? Adjudication can produce a fast interim payment determination between contract parties. A payment bond remains a separate instrument with its own claimants, notices and suit limits. Faster disputes may change timing pressure around bond claims; they do not rewrite the bond. Read the bond, the contract and counsel’s advice together.
Will the Act apply to contracts already signed before the force date? Section 50 says the Act will not apply to a contract entered into before that section comes into force, or to a related subcontract. Regulations may also phase application by sector or ownership class under section 51. Confirm the commencement regulation and any transition schedule when they are published.
Where should I start if I only need the Ontario vs BC status snapshot? Use our shorter briefing on Canada construction payment rules for Ontario and BC, then return here for the BC statute deep dive and surety watch-outs.