How Canada's federal prompt payment law works on federal construction: 28-day clock, notices of non-payment, CanDACC adjudication, holdback and payment bonds.
Education only / verify at source / not legal advice. This guide explains the Federal Prompt Payment for Construction Work Act and its three sets of regulations as they read on Justice Laws (Act current to October 19, 2026, last amended December 9, 2023; regulations current to the same date). Every rule cited comes from a public source retrieved on November 13, 2026 (PT), listed at the end; statutes and regulations are cited from Justice Laws. Global Guarantors publishes industry education. We aren't a surety, broker, government agency, adjudicator or law firm. The statute, the regulations, your contract, your bond wording and your own lawyer's advice control.
Start here: Surety 101: three parties, one written promise · Contract surety hub · Lien bonds and vacating liens in Canada
Most Canadian prompt payment talk is provincial. Ontario switched its regime on in 2019, Alberta and Saskatchewan followed in 2022, and British Columbia passed its own act in 2025. Federal construction sits on top of all of that. When the work is on federal real property or a federal immovable (a federal office building, a military base, a port, a border crossing, a national park asset), a separate federal statute sets the payment clock and gives unpaid contractors and subcontractors a fast, binding route to an adjudicator.
That statute is the Federal Prompt Payment for Construction Work Act (in this guide, "the federal Act"). It was enacted in 2019 as part of a budget bill and came into force on December 9, 2023. Contracts already signed by then got a one-year grace period, so since December 2024 the federal regime has applied to essentially every live federal construction contract and its subcontracts.
For the surety market the federal Act matters in three ways. It changes when money moves down a federal chain, which is what labour and material payment bonds protect. It creates binding adjudicator decisions that can land on a bonded contractor quickly. And it gives an unpaid party a statutory right to suspend work. This page covers the law first and the bonding consequences second.
This page does not publish premiums, ratings or company-specific figures. Any number quoted comes from a cited public source and is dated.
Section 5 says the Act applies to the Crown, to any service provider and to any contractor or subcontractor performing construction work "for the purposes of a construction project located in Canada in respect of any federal real property or federal immovable." Those terms come from the Federal Real Property and Federal Immovables Act.
A construction project under section 2 means work required by a contract with the Crown or a service provider for:
Capital repair is defined to mean repair that extends the normal useful life or improves the value or productivity of the property. Maintenance or repair that prevents normal deterioration is excluded. That line matters for facility-maintenance contracts: routine upkeep may fall outside the Act while a roof replacement under the same contract may fall inside it.
Construction work includes the supply of materials, services and equipment rental, so suppliers and equipment renters are in the chain, not only trades.
Lessors and lessees of the property are carved out of the contractor and service provider definitions, so a landlord's renovation of space the Crown leases is generally outside the federal Act. Employees are excluded too (section 2(2)).
Before the Crown or a service provider signs a construction contract, it must tell the contractor that the Act will apply. Every contractor and subcontractor must do the same down the chain (section 8). Section 5 does not make the Act's application depend on that notice, so a subcontractor that was not told should still check whether the property is federal.
Section 25 kept the Act off, for one year after December 9, 2023, for prime contracts signed before that date and for subcontracts under them signed before or within that year. That window closed in December 2024; transition questions on older long-running contracts are for counsel.
The Governor in Council can exempt a specific project by order (section 7). We did not find any exemption orders listed among the Act's regulations on Justice Laws on November 13, 2026; check the "Regulations made under this Act" list before relying on that.
Section 6 lets the Governor in Council designate a province whose own prompt payment and adjudication laws are "reasonably similar." The criteria in SOR/2023-269, s. 2 are a proper-invoice concept, tiered payment deadlines, a notice-of-non-payment mechanism, adjudication on similar timelines, and binding determinations.
The designation order (SOR/2023-270) names Ontario, Saskatchewan and Alberta. It came into force with the Act on December 9, 2023 and showed no amendments when we checked Justice Laws on November 13, 2026.
Designation does not hand the whole project to the province. Under section 6(2)(a), subsections 8(2) and 9(5), sections 10 to 14 and subsection 16(5) "no longer apply to any contractor" on a project there, but the rest of the Act, including the Crown's 28-day duty and the right to adjudicate in section 16(1), still does. Under section 6(2)(b), the Act no longer applies at all to subcontractors or to a service provider that pays for the work.
| Relationship | Designated province (ON, SK, AB) | Any other province or territory |
|---|---|---|
| Crown to prime contractor | Federal Act, minus the contractor provisions switched off by s. 6(2)(a) | Federal Act |
| Service provider to prime contractor | Federal Act no longer applies to the service provider | Federal Act |
| Prime contractor to subcontractors, and below | Federal Act no longer applies to subcontractors; the provincial regime is the reference point | Federal Act |
Because sections 12 (holdback) and 14 (interest) are on the switched-off list, how holdback and interest work between the Crown and a prime contractor in a designated province is a question for counsel. The Governor in Council can adapt the provisions that still apply to resolve conflicts with provincial law (s. 6(2)(c)). A project that straddles a provincial border is outside section 6(2) altogether, so the federal Act applies in full (s. 6(3)).
British Columbia. BC's Construction Prompt Payment Act received Royal Assent on November 27, 2025 but was not yet in force when we last checked (see our BC prompt payment explainer). Until BC's regime is in force and Ottawa designates it, federal projects in BC, as in every other non-designated province and territory, follow the federal Act all the way down the chain.
Everything runs off the proper invoice. Under section 9(1) the contractor submits one monthly, or as the contract says, covering unpaid work by it and by subcontractors in the chain up to the invoice date.
SOR/2023-271, s. 2 adds the required contents: the invoice date and the contractor's contact details; the supply period; the contract number or other authorization; a description of the materials or services, with quantities where applicable; the amount payable and payment terms; and the payee's name, title and contact details.
Two points carry most of the weight:
Subcontractors have a right to know when the clock started. On request, the contractor must tell any subcontractor in the chain the date the owner received its proper invoice (section 9(5)). For its own construction-related contracts of $100,000 or more, PSPC publishes a weekly-updated table of vendor, payment date and proper-invoice received date (retrieved November 13, 2026).
All deadlines count from the day the Crown or service provider received the prime contractor's proper invoice. They do not restart at each tier.
| Tier (Act section) | Must pay no later than | Notice of non-payment no later than |
|---|---|---|
| Crown or service provider to contractor (s. 9(2), (3)) | Day 28 | Day 21 |
| Contractor to first-tier subcontractors (s. 10(1), (3)) | Day 35 | Day 28 |
| First-tier to second-tier (s. 11(1), (3)) | Day 42 | Day 35 |
| Second-tier to third-tier (s. 11(4)) | Day 49 | Day 42 |
| Each further tier (s. 11(4)) | Seven more days | Seven more days |
SOR/2023-269, s. 3 says the following "are excluded from the computation of time for the purposes of the time limits referred to in sections 9 to 11 of the Act":
So the 28 days are counted days, not calendar days, and the holiday list depends on where the project is. PSPC's December 2023 news release summarized the Crown's deadline as "28 calendar days." The regulation is the binding text. The rule covers only the payment and notice deadlines in sections 9 to 11, so do not assume it stretches other deadlines in the Act (see the adjudication section). Check the regulation and your contract before you diarize a deadline.
The contractor's and subcontractors' payment duties are triggered by being paid. A contractor that is "paid by Her Majesty or a service provider under subsection 9(2)" must pay its subcontractors for work they invoiced, that was covered by the proper invoice and that the owner paid for (section 10(1)). Each lower tier works the same way.
Money the owner releases for a subcontractor's work must reach that subcontractor within a fixed window. Section 10(1) does not, by itself, require payment for work the owner never paid for. That is where adjudication and, ultimately, the payment bond come in.
A payer withholding all or part of an invoice must send a notice of non-payment within its window. Section 13 and SOR/2023-271, s. 3 require:
A contractor that received a notice from the owner can pass the shortfall down with its own notice within its window; section 13(c) expressly contemplates that reason.
If a contractor is only paid in part, section 10(2) sets an order of distribution:
Section 11(2) applies the same order one level down. The Act therefore limits how freely a contractor can redirect a partial payment from the owner.
The federal Act does not set its own holdback percentage. Section 12 allows each payment to be subject to a contractual holdback, with two limits:
Outside the designated provinces, that ties federal holdback to the local lien or construction statute. In Ontario, Saskatchewan and Alberta, section 6(2)(a) switches section 12 off for the contractor, so the provincial statute and the contract do more of the work; counsel should confirm how they apply to a federal site. For Ontario's own rules, see our Ontario holdback explainer.
Pending bill, not law. Ontario's Bill 140, the Building Ontario Faster Act, 2026, would amend the Construction Act's annual holdback rules (section 26) so that owners prescribed by regulation could use a fixed annual date instead of the contract anniversary, with transition changes to section 87.4. As of November 17, 2026 it was before the Standing Committee on the Interior, which was holding public hearings on that day, and it had not become law. It does not change the federal Act or Ontario's 28-day clock. Check its status on the Legislative Assembly's bill page (Sources) before relying on Ontario holdback timing.
Interest runs from the statutory (or shorter contractual) deadline on amounts not covered by a notice of non-payment, on amounts withheld only because the payer itself got a notice from above, and on other disputed amounts to the extent an adjudicator orders them paid (section 14(1)).
The rate is the prescribed rate or the contract rate, whichever is greater (section 14(2)). SOR/2023-269, s. 4 prescribes simple interest equal to the average Bank of Canada bank rate plus 3 percent a year, averaging the bank rates set in the month before the month being calculated.
Section 15 lets the Minister designate an Adjudicator Authority. Canada Dispute Adjudication for Construction Contracts (CanDACC) describes itself as "the Adjudicator Authority under the Federal Prompt Payment for Construction Work Act" and keeps the adjudicator registry. Its 2025 Annual Report says ADR Chambers Inc. "was appointed as the Adjudicator Authority" on July 17, 2023, that CanDACC began operating on December 9, 2023, and that CanDACC is a division of ADR Chambers Inc. PSPC's December 12, 2023 news release says the government awarded ADR Chambers Inc. a contract in August 2023 to provide adjudication services and oversee the process.
The same report shows low volume so far: none commenced in 2024, six in 2025, and three determinations taking 81, 90 and 171 calendar days.
Under SOR/2023-271, ss. 4 and 5, the Authority trains, certifies and disciplines adjudicators, publishes a fee schedule and a public registry, and appoints adjudicators when parties cannot agree. To be designated, an adjudicator needs at least 10 years of relevant construction-industry experience, must be accredited with the Authority, must not have been convicted of an indictable offence or be an undischarged bankrupt, and must hold the security clearance the dispute requires. That condition reflects federal work, where some projects involve classified information.
A contractor or subcontractor that has not been fully paid within the statutory (or shorter contractual) deadline can refer the non-payment dispute to an adjudicator (section 16(1)). It starts by giving the payer a notice of adjudication naming the parties, describing the dispute, stating the amount claimed and proposing an adjudicator from the registry (section 16(3)). A contract cannot restrict the choice of adjudicator to a narrower list (section 16(4)). CanDACC's site says the claimant also sends it an electronic copy of the notice.
The notice must be given no later than the 21st day after the later of:
A subcontractor can ask the contractor for the date the certificate of completion was received (section 16(5)). The day-exclusion rule in SOR/2023-269, s. 3 is written for sections 9 to 11, so do not assume it extends this 21-day window; count conservatively. Missing the window does not erase the debt, but it removes the fast statutory route.
The steps below come from SOR/2023-271. Section 8 of those regulations excludes the same days (holidays, Saturdays, December 24 to January 1 and provincial construction holidays) from these steps. The final 10-day payment deadline is in the Act itself, so the regulations' exclusions are not stated to apply to it.
| Step | Deadline | Regulation |
|---|---|---|
| Parties jointly approach an adjudicator | Within 4 days after the notice of adjudication is received | s. 13(1) |
| Adjudicator consents or refuses | Within 4 days of the request | s. 13(2), 14(2) |
| If no joint appointment, Authority appoints | Within 5 days of a written request | s. 15(2) |
| Authority tells parties who was appointed | Within 2 days of appointment | s. 15(3) |
| Claimant sends notice, statement of facts and documents | Within 5 days after consent is received | s. 16 |
| Respondent's statement and materials | Within 20 days after receiving the claimant's documents | s. 18 |
| Written determination with reasons | Within 20 days after the response (or after it was due) | s. 22(1) |
| Extension | Up to 5 days by the adjudicator, longer with everyone's consent | s. 22(2) |
| Certified copy to parties | Within 5 days after the determination | s. 25 |
| Payment of any amount ordered | Within 10 days of receiving the determination (or as the determination says) | Act s. 19(1) |
Other procedural rules:
A determination binds the parties unless they agree otherwise in writing or it is set aside by a court order or arbitral award (Act s. 18(2)). Nothing in the Act stops a court or arbitrator from deciding the merits afresh later (s. 18(3)). In other words, adjudication is "pay now, argue later." That is the same interim-finality model used in Ontario, Saskatchewan and Alberta.
If a party ordered to pay does not pay within the deadline, the party owed may do two things (section 19(2)):
The federal Act says nothing about bonds. Federal construction contracts do, through their contract security terms.
PSPC's standard construction general conditions include GC9, Contract Security (clause R2890D in the Standard Acquisition Clauses and Conditions (SACC) Manual). CanadaBuys says the SACC Manual has not been maintained since June 2023 and its clauses are archived, though contracts issued with them remain valid. The archived R2890D (version dated December 1, 2022) says:
Individual solicitations change these terms. One dated example: a contract security document published with CanadaBuys tender notice 107906 (PDF created March 2022) uses an older "CS1/CS2" structure. In that document, security is optional below $25,000 and mandatory at $25,000 or more, and a security deposit scale (capped at $250,000) can replace the performance bond. A Parks Canada tender posted on CanadaBuys in October 2026 (Hattie Cove) marks GC9 "Not applicable" and states that bid and contract security are not required for that project. Other federal buyers, such as Defence Construction Canada, may use their own documents. Always read the specific solicitation.
PSPC tied bonds to subcontractor protection well before the federal Act. Its June 8, 2017 release said PSPC-managed construction contracts over $100,000 require contract security "(such as bonds) to protect subcontractors against non-payment."
When the bonds end. CanadaBuys' buyer guidance on financial security says surety bonds expire automatically and must be destroyed once the contractor has met all contractual obligations, while security deposits are returned if the contract ends without fault on the contractor's part (retrieved November 13, 2026). Our guide on how surety bonds end, linked under Related reading, covers the general concepts.
For the standard private-sector Canadian forms, see our CCDC 221 and 222 guide. Federal bond forms differ in wording from CCDC forms, so the claim mechanics below are general.
The federal Act makes money move faster and makes disputes cheaper to decide. It does not guarantee that the party who owes the money can pay it. If a contractor becomes insolvent, an adjudicator's determination against it is a judgment-like piece of paper against an empty company. The labour and material payment bond is the asset that remains.
Under the archived GC9.2, a payment bond is at least 50 percent of the Contract Amount. Whether a particular claimant is covered, how much it can recover and what notice it must give depend entirely on the bond wording. Canadian payment bonds commonly limit claimants to those with a direct contract with the principal or with a subcontractor of the principal, and set written-notice and suit deadlines. Our subcontractor payment bond claim guide explains the usual structure. Read the actual bond.
The federal Act also changes the facts a performance bond surety may face after a default notice.
This is our editorial view, not a description of how any surety prices or underwrites. Our bonding capacity guide (see Related reading) covers the general concepts. The federal Act suggests some questions a reader might ask about a contractor with federal work:
This is a high-level, dated comparison. Each provincial regime has transition rules, exceptions and amendments not shown here. Use our Ontario and BC prompt payment page and the official sources for detail.
| Regime (in force) | Owner pays proper invoice | Adjudication body |
|---|---|---|
| Federal, federal real property (December 9, 2023; one-year transition) | 28 counted days (Saturdays, holidays, Dec 24 to Jan 1 and construction holidays excluded); then seven-day steps | CanDACC (Adjudicator Authority) |
| Ontario, Construction Act (October 1, 2019; further amendments January 1, 2026) | 28 days | ODACC |
| Saskatchewan, Builders' Lien Act Part II.1 (March 1, 2022, for later contracts) | 28 days; contractor pays subcontractors within seven days of being paid | SCDRO |
| Alberta, Prompt Payment and Construction Lien Act (August 29, 2022, with transition) | 28 calendar days | Nominating Authorities appointed by Alberta |
| British Columbia, Construction Prompt Payment Act (Royal Assent November 27, 2025; not in force on November 13, 2026) | Not yet operative | Not yet designated |
Provincial rows: ODACC, the Saskatchewan government and SCDRO, Alberta's prompt payment page, and BC Laws, checked November 5 to 13, 2026.
Before you rely on anything above on a live federal project:
Does the federal Act apply to every project the federal government funds? No. It applies to construction projects on federal real property or federal immovables under a contract with the federal Crown or a service provider. A provincially or municipally owned project that receives federal infrastructure funding is generally governed by provincial law.
How long does the Crown have to pay? 28 counted days after receiving a proper invoice, or it must send a notice of non-payment by day 21. The contractor then pays its subcontractors by day 35, and so on in seven-day steps.
Who runs federal construction adjudication? CanDACC, the Adjudicator Authority under the Act. CanDACC's 2025 Annual Report describes it as a division of ADR Chambers Inc., which it says was appointed Adjudicator Authority on July 17, 2023.
How long does adjudication take? Adding up the regulatory steps gives a little over 50 counted days from the notice of adjudication to a determination when the parties appoint jointly, a few more if CanDACC appoints, plus any extension. Because weekends and holidays don't count, that is longer on the calendar. CanDACC's 2025 report lists three determinations that took 81, 90 and 171 calendar days. Payment is due within 10 days of receiving the determination.
What if a determination is not paid? The party owed can suspend work without breaching its contract and can file the determination in the Federal Court or a provincial superior court within two years to enforce it.
Does adjudication replace a payment bond claim? No. Adjudication decides what is owed between contracting parties. A payment bond is security for that debt if the party who owes it cannot pay. Keep both deadlines.
Does the federal Act apply in Ontario, Saskatchewan or Alberta? Partly. The Crown's duty to pay the prime contractor and the prime's right to adjudicate stay federal. The Act no longer applies to subcontractors or service providers there, unless the project straddles a provincial border.
Is BC designated? Not as of November 13, 2026. BC's own act was not yet in force.