CCDC 221 and 222 in Canada: 2024 performance and payment-bond claims clocks, Ontario Forms 31 and 32, and federal PWGSC 505 and 506.
Education only / verify at source / not legal advice. This guide explains the two standard Canadian contract-surety bonds most often specified after a construction tender is awarded: the CCDC 221 performance bond and the CCDC 222 labour and material payment bond, in their 2024 editions. It is grounded in public CCDC pages, public specimens hosted by the Surety Association of Canada, an Alberta Infrastructure specification, Ontario's Construction Act and forms regulations, and federal public form text. Official CCDC fillable forms are sold only through authorized outlets; Global Guarantors does not host or reproduce the licensed form text. Where this page describes a specimen, it paraphrases structure and clocks rather than reprinting the instrument. Global Guarantors publishes industry education. We aren't a surety, broker or law firm, and we don't publish premiums. The bond actually issued, the bid or contract documents, the governing law and your own lawyer's advice control.
Start here: Contract surety hub · Surety glossary · Surety 101: three parties, one written promise
A bid bond gets a Canadian contractor to the award table. What the owner usually wants next is a pair of post-award bonds: a performance bond, so a surety stands behind the contractor's promise to perform the contract, and a labour and material payment bond, so unpaid subcontractors and suppliers have a written claim path that does not depend on liening public land.
In many tenders that pair is the CCDC family. CCDC describes CCDC 221 – 2024 as a "standard surety performance bond form guaranteeing performance of the contract by the Contractor," and CCDC 222 – 2024 as a "standard surety labour and material payment bond form guaranteeing that the Contractor will satisfy all labour and material payment obligations incurred in performing the contract." Those official one-sentence descriptions sit on the CCDC 220 / 221 / 222 – 2024 Bond Forms page. This is the post-award companion to our bid bonds in Canada and CCDC 220 guide. It does not reprint CCDC's licensed wording. It walks the 2024 public specimens and contrasts them with Ontario's prescribed Forms 31 and 32 and with federal PWGSC-TPSGC 505 and 506. Payment-bond disclosure after Valard v. Bird, lien bonds and prompt-payment regimes already have their own pages.
The Canadian Construction Documents Committee publishes standard construction contracts and a three-form surety set: CCDC 220 (bid), CCDC 221 (performance) and CCDC 222 (labour and material payment). The current editions are the 2024 bond forms. Official fillable PDFs are sold through authorized document outlets; CCDC's FAQ explains the purchase path. This site does not host the forms.
The Canadian Construction Association published a news post on May 23, 2024 (UTC), announcing a group of new CCA and CCDC documents "as of May 21," including "CCDC 220, 221, 222 – 2024 ‘Bond Forms’." CCA writes that those forms "have been updated to incorporate the Ready-for-Takeover project milestone and introduce further clarity, collaboration, and responsiveness on the part of the surety." Ready-for-Takeover is a contract milestone used in the CCDC 221 – 2024 suit-limitation clause; the bond does not define the contract conditions that make it up.
The Surety Association of Canada hosts public specimen PDFs of the 2024 bonds for education (file names dated 2024-04-02, each marked Copyright 2024 and approved by SAC). Those specimens are not a substitute for a purchased official instrument. The next two sections paraphrase them rather than reprint them. SAC also maintains a public education page on the 2024 forms, cited here as a source URL only. Some projects still specify the 2002 editions; do not assume a 2024 clock or trust clause is on a bond that has not been issued in that edition. Our CCDC 221 – 2024 wordings card and the companion 222 card record the edition and the purchase path without hosting the licensed text.
Neither CCDC 221 nor CCDC 222 states a mandatory percentage of the contract price. The Bond Amount is a blank on the specimen, filled by the bid documents, the contract or a statute that actually applies. Canadian public tenders often call for these bonds at about 50 percent of the contract price, and sometimes at 100 percent. That "about half" figure is common tender practice, not a pan-Canadian rule.
A specification example, not a provincial law. Alberta Infrastructure's Basic Master Specification section 00 61 13, Contract Performance Security, dated 2022-10-31, is to be used as written. In the situations it covers, the contractor must provide a CCDC 221 performance bond for 50 percent of the Contract Price, issued by a surety authorized in Alberta, consigned to His Majesty the King in right of Alberta, as represented by the Minister of Infrastructure, and submitted within 15 Days after the date of the Letter of Acceptance of bid. The cover sheet tells editors normally to specify this security when the estimated contract cost is $100,000 or greater. That is ministry guidance, not a statute, and the section as fetched names a performance bond only — not also a CCDC 222.
Ontario and federal percentages sit on other forms. Ontario sets a statutory floor on prescribed Forms 31 and 32 for public contracts to which Construction Act section 85.1 applies — not on CCDC 221 and 222. SACC items E0007C and E8000C (both listed active 2022-12-01) use fill-in-the-blank percentages and name PWGSC-TPSGC 505 and 506. When writing or bidding a tender, name the form edition, the Bond Amount or percentage, the obligee's exact legal name, and whether both bonds are required; do not assume a CCDC 221 / 222 pair at 50 percent will be accepted.
The CCDC 221 – 2024 public specimen names the Principal, the Surety and the Obligee, states a Bond Amount, and incorporates the written contract, including amendments, as the Contract. The obligation is void if the Principal promptly and faithfully performs the Contract; otherwise it remains in force, subject to the numbered conditions and three schedules: Notice (Schedule A), acknowledgement (Schedule B) and the surety's Position (Schedule C). The map below is from that public specimen. It does not apply to a 2002 edition, an Ontario Form 32, a federal 505 or a manuscript bond.
The specimen is notice-driven. Except for a pre-notice meeting under section 2.1, the surety has no obligation under the bond until it receives a written Notice substantially in the form of Schedule A. Notice to the first listed surety is enough if there is more than one. Section 2 lets the obligee, acting reasonably, request a pre-notice meeting by notifying the surety and the principal in writing that it is considering declaring the principal in default. That request is not a Notice, is not notice under the Contract, and is not a precondition to giving Notice; participation is without prejudice; and if a Notice arrives first, the request is deemed retracted. Once a Notice arrives, section 3 requires the surety promptly to investigate, using its best efforts, whether the conditions precedent have been satisfied and what liability, if any, it has. The obligee is to provide requested information and site access promptly, in accordance with the Contract, where they are in its possession or control.
| Step in the 2024 specimen | Clock | What it is |
|---|---|---|
| Pre-notice meeting (s. 2) | Surety proposes a meeting within 7 business days of the request, or longer if all parties agree | Optional; not a Notice |
| Acknowledgement (s. 3.2) | Within 4 business days after the surety receives the Notice | Schedule B, plus a request for information and access |
| Surety's Position (s. 3.3) | No later than 20 business days after receipt of the Notice, or longer if agreed | Schedule C: accept, decline with reasons, or unable to determine |
| Investigation status meeting (s. 3.4) | Within 5 days after the obligee's request | Written as "five days," not "five business days" |
| Post-notice conference (s. 5.1) | Surety proposes a conference within 5 business days, or longer if agreed | Used to identify Mitigation Work |
| Notice of Necessary Interim Work (s. 4) | Written notice to the surety within 3 Business Days of commencement | Safety, preservation of the work, or compliance with law |
During the investigation, section 4 lets the obligee, acting with due diligence and giving written notice within three Business Days of starting, undertake Necessary Interim Work required for safety, to preserve the work, or to comply with law. Section 5 lets the obligee proceed with Mitigation Work if it shows the work is necessary and the costs are reasonable, paying first, keeping separate records and giving the surety access. The surety may object in writing; the obligee may still proceed. Reasonable costs are reimbursable if liability is later established, those payments reduce the Bond Amount, and the fact that the work proceeded is not, by itself, a defence.
If the surety has accepted liability, section 6.1 requires it promptly to select and commence one of four options: remedy the default; complete the Contract; obtain bids and arrange a completion contract with the lowest responsible bidder determined by the obligee and the surety, making sufficient funds available as work progresses (including applicable value-added taxes, less the Balance of Contract Price); or pay the lesser of the Bond Amount or the obligee's Direct Expenses plus the proposed cost of completion and any such taxes, less that balance.
Direct Expenses under section 7.1, without duplication, include reasonable professional and external legal fees incurred to complete the Contract as a direct result of the default (except fees to defend or pursue a claim or action by or against the principal), reasonable out-of-pocket expenses, direct costs of an extended supply period as defined in section 7.2, reasonable interim and mitigation costs, and any further fees the three parties agree. They may be deducted from the Balance of Contract Price or reimbursed by the surety, and they reduce the Bond Amount. Section 7.3, subject to any agreement to the contrary, excludes liquidated damages, other delay or non-performance damages except as provided in section 7.1(d), and indirect or consequential damages such as financing, hedging, lost profit or head office overhead. Do not assume delay liquidated damages are covered.
Section 8.1 sets four conditions precedent: a declared default, any contract-required notice of default, performance of the obligee's own obligations, and agreement to pay the Balance of Contract Price to the surety or as the surety directs. That balance is the total amount payable to the principal, including adjustments, reduced by deducted Direct Expenses and by valid and proper payments already made. Under section 9.2 it is used first to mitigate potential loss under this performance bond and then under any labour and material payment bond issued by the same surety for the Contract. The surety is not liable for more than the Bond Amount (s. 10.1). For any surety option or Direct Expenses, its responsibility is secondary to, and not greater than, that of the Principal; insolvency does not reduce a sum the principal must pay, except to the extent the obligee compromises it without the surety's prior approval (s. 10.2). Only the named obligee and its successors have a right of action (s. 11).
Section 12.1 requires any suit or action to be commenced before two years from the earlier of: (a) if the Contract contains Ready-for-Takeover requirements as defined in a CCDC contract, the earlier of the Ready-for-Takeover date and 180 days after substantial performance of the work under the lien legislation where the work is taking place, provided the obligee has given the surety a copy of the written Ready-for-Takeover confirmation within ten business days after it was issued under the Contract; (b) if those requirements are absent, or if that confirmation is late, the date of substantial performance of the Contract under that lien legislation; or (c) the date the surety received the Notice under section 1.1 for the default in issue. Suits are to be brought where the work is taking place, notwithstanding contrary terms in the Contract.
In Québec, section 12.3 states a different coverage-period rule: the period begins at the date of commencement of the Contract work and ends two years following acceptance of that work under Civil Code article 2110, and only defaults the obligee declares in writing to the principal during that period are covered. An unofficial paraphrase of article 2110 is under What to verify; confirm the official Civil Code text and the issued bond if the project is in Québec.
The CCDC 222 – 2024 public specimen is a payment bond with its own Notice of Claim, acknowledgement and Position schedules. The recitals say the bond is for the benefit of the Obligee, incorporate the Contract, and make the obligation void if the Principal pays all Claimants, as defined, for labour and material used or reasonably required for use in performing the Contract.
Section 1 defines a Claimant as every corporate or natural person having a direct contract with the Principal for labour, material or both used or reasonably required for use in the performance of the Contract. Labour and material include stated utility and rental items, and rent-to-purchase equipment claims are limited to the prevailing industrial rental value for the period of use. On this wording, a claimant is first-tier; a lower-tier supplier with no direct contract with the principal should not assume it is a Claimant under CCDC 222 – 2024. A Claimant unpaid after the due date under its contract with the Principal may demand payment by a written Notice of Claim substantially in Schedule A, copied to the principal and the obligee.
Section 7 makes a timely Notice of Claim a condition precedent. For Holdback — the amount required to be held back from the Claimant under its contract or under the applicable lien legislation, whichever is greater — the notice is due within 120 calendar days after the Claimant should have been paid in full under its contract with the Principal. For any other amount, it is due within 120 calendar days after the date the Claimant last performed labour or provided materials for which the notice was given.
| Step in the 2024 specimen | Clock | What it is |
|---|---|---|
| Notice of Claim (s. 7) | 120 calendar days (holdback and non-holdback rules differ; see above) | Condition precedent; Schedule A, copied to the principal and the obligee |
| Acknowledgement (s. 8(a)) | 3 business days after the surety receives the Notice of Claim | Schedule B, plus any request for information |
| Surety's Position (s. 8(b)) | The earlier of 10 business days after that information, 25 business days after the Notice of Claim, or a longer time agreed with the Claimant | Schedule C |
| Payment of undisputed amounts (s. 9) | 10 business days after the Position is provided | Without prejudice to disputed amounts; court application exception in s. 11 |
The Bond Amount is a hard ceiling (s. 10). Payments reduce it (s. 11). If the aggregate of Notices of Claim exceeds the Bond Amount, or the surety believes claims that might still be notified would, the surety may apply to the court for direction in the interest of all Claimants. On payment, the surety is subrogated to the Claimant's rights, and the Claimant undertakes to extend warranties for labour and materials for which it has been paid (s. 12). Notices to a first-listed co-surety count for all (s. 6).
Sections 3 to 5 deal with a narrow trust and with what it does not require of the obligee. Where a Claimant is prohibited by law from suing to enforce payment under the bond, the principal and surety agree that the obligee holds the bond in trust so the Claimant can start that suit. Section 4 says the bond or that trust does not impose on the obligee any duty to a Claimant, including any obligation to notify a Claimant that the bond or the trust exists. Section 5 says the obligee need not proceed against the surety on a Claimant's behalf. Those sections are the 2024 form's response to the disclosure issues that followed Valard Construction Ltd. v. Bird Construction Co., 2018 SCC 8, which concerned a CCDC 222-2002 bond. Our Valard and payment-bond disclosure guide is the deep dive. Older 2002-edition bonds, and some modified forms, may still omit section 4. Whether section 4 fully displaces the Valard duty remains a counsel question.
Section 13 makes it a condition precedent that any suit or action under the bond be commenced within one year after the date on which the Principal last performed work on the Contract, including work performed under any warranty or guarantees provided in the Contract. In Québec, the coverage period expires one year after that same last-work date, including warranty or guarantee work — a different pointer from CCDC 221's article 2110 rule. Suits are to be brought where the work is taking place (section 14).
On many Ontario public jobs the required instruments are not CCDC 221 and 222 but prescribed court-form bonds under Part XI.1 of the Construction Act, R.S.O. 1990, c. C.30.
Section 85.1 applies, subject to the regulations, to a public contract — a contract between an owner and a contractor respecting an improvement, where the owner is the Crown, a municipality or a broader public sector organization — if the contract price exceeds the prescribed amount. It does not apply where the contractor is an architect or an engineer. On a covered contract the contractor must furnish the prescribed labour and material payment bond, extending protection to subcontractors and persons supplying labour or materials to the improvement, and the prescribed performance bond, each of an insurer licensed under the Insurance Act to write surety and fidelity insurance. Coverage limits sit in the regulations; a prescribed form may set out the claims process; and the owner may still require other bonds or security (s. 85.1(7)).
O. Reg. 304/18, section 12, applies section 85.1 if the contract price is $500,000 or more. Section 12.1, added by O. Reg. 260/24, sets the minimum coverage limit for each bond at 50 percent of the contract price, except that if the contract price is more than $500,000,000, the owner specifies a limit of at least $250,000,000, and only if the two bonds and any other required security, taken together, would "reflect an appropriate balance" between the adequacy of the security and its cost.
O. Reg. 303/18, section 2(27) and (28), require Form 31 for the payment bond (version 2025/11 in the Table of Forms fetched November 10, 2026) and Form 32 for the performance bond (version 2019/08). Those are public court forms, not CCDC forms.
Section 85.2 gives a payment-bond beneficiary a right of action against the surety and the principal, and the owner a right of action on the performance bond, each in accordance with the bond, if the principal or contractor defaults. The surety is not liable for more than it undertakes to pay, is not made the principal or a party to the contract, and is subrogated to the rights of the person paid. Where section 85.1 applies, use Forms 31 and 32 and the section 12.1 floors, not a CCDC default. Confirm the solicitation.
Federal construction and many other Crown contracts use Public Services and Procurement Canada standard forms, not CCDC. The performance bond is PWGSC-TPSGC 505. The labour and material payment bond is PWGSC-TPSGC 506, named in SACC item E8000C (listed active 2022-12-01). E8000C requires a 506 in a stated percentage of the Contract Price, accepted by a company on the federal source list, within a stated number of calendar days after award; a copy must be posted in a plainly visible place where any of the Work is performed; and Canada may terminate for default if the bond is late. E0007C (also listed active 2022-12-01) requires, within a stated number of calendar days after award, a 505, a 505 and a 506 together, a 506 alone, or a security deposit, each in a stated percentage of the Contract Price.
The 505 form is published as public form text on Canada.ca. In the version reviewed November 12, 2026, the obligee is His Majesty the King in right of Canada. When the principal is, and is declared by the Crown to be, in default, the surety's duties turn on whether the work is taken out of the principal's hands and whether the Crown directs the surety to complete. If the surety or a completion contractor finishes the work, the completing party must comply with the Ineligibility and Suspension Policy. The surety is not liable for more than the amount specified in the bond, and the Crown must sue, if at all, within two years from the date on which final payment under the Contract is payable — not the CCDC 221 Ready-for-Takeover or substantial-performance clock. This page does not reprint the 506 form. For payment-bond information rights on federal work, including the Financial Administration Act assignment discussed in Valard, use the Valard guide. US federal construction, by contrast, generally requires performance and payment bonds at 100 percent of the original contract price under FAR 28.102-2, with a stated exception if the contracting officer determines a lesser amount; see our Miller Act and little Miller Act guide.
Provincial prompt-payment rules set invoices, payment deadlines and interest; they do not replace a payment bond. Ontario holdback, including annual release, is statutory holdback, not the Bond Amount on a CCDC 222. See the Canada prompt payment guide (Ontario and BC) — and check that page before assuming a British Columbia prompt-payment right is already in force — and the Ontario holdback page in Related reading. A lien bond in Canada is posted after a lien is registered, to vacate that lien; a performance or payment bond is placed before trouble starts. The CCDC 222 – 2024 specimen looks through to lien legislation only to define Holdback for the 120-day notice rule, not to discharge holdback.
When writing or bidding the tender
When a performance concern is brewing (CCDC 221 – 2024)
When a payment-bond claim is in view (CCDC 222 – 2024)
What is the difference between a CCDC 221 performance bond and a CCDC 222 labour and material payment bond? CCDC 221 is a performance bond for the named obligee, typically the owner. CCDC 222 is a labour and material payment bond for defined claimants. On the 2024 CCDC 222 specimen, a Claimant has a direct contract with the principal. Neither bond replaces the other.
Do CCDC 221 and 222 always have to be for 50 percent of the contract price? No. The CCDC forms leave the Bond Amount blank. Fifty percent appears in some public specifications, including Alberta Infrastructure section 00 61 13 where that section applies, and as Ontario's ordinary minimum on Forms 31 and 32 for public contracts of $500,000 or more.
Is a CCDC 221 or 222 accepted on every Canadian public job? No. Ontario public contracts to which Construction Act section 85.1 applies require Forms 31 and 32. Federal Crown work uses PWGSC-TPSGC 505 and 506 when the SACC clauses say so.
How quickly must a surety respond to a CCDC 221 – 2024 Notice? In the public specimen, acknowledgement is due within four business days and the written Position within twenty business days after receipt, unless a longer period is agreed. A post-notice conference is to be proposed within five business days. A requested pre-notice meeting is to be proposed within seven business days and is not itself a Notice.
Who can claim on a CCDC 222 – 2024 payment bond? On the public specimen, a Claimant has a direct contract with the Principal for labour, material or both used or reasonably required for use in performing the Contract. A lower-tier supplier that contracted only with a subcontractor should not assume it is a Claimant under this form. Notice of Claim is due within 120 calendar days, with a separate holdback rule.
Does CCDC 222 – 2024 require the owner to tell subcontractors the bond exists? Section 4 of the 2024 specimen says the bond or the limited trust in section 3 does not impose on the obligee any obligation to notify a Claimant that the bond or the trust exists. Statutory rights to ask about a payment bond can still apply; those rights, and Valard, are covered in our Valard guide.