Subdivision and site-improvement bonds in the United States

US subdivision and site-improvement bonds: California Government Code Chapter 5 amounts and release clocks, Texas county bonds, and Florida's pre-plat permit bond.

Subdivision and site-improvement bonds in the United States

Published: November 13, 2026 · Last verified: November 13, 2026 (PT)

Education only / verify at source / not legal advice. This guide explains how selected US statutes treat surety bonds and other security for a developer's off-site and on-site public improvements — streets, drainage, utilities and similar works — as a condition of a subdivision or related development approval. It is grounded in California Government Code Chapter 5 (Improvement Security), Texas Local Government Code Chapter 232 (county subdivision platting), and Florida Statutes section 177.073 (a statewide program for expedited residential building permits before a final plat is recorded). Those three sources are not a fifty-state code. Local ordinances, city subdivision manuals and other state chapters can add, replace or waive what is described here. Global Guarantors publishes industry education. We aren't a surety, broker or law firm, and we don't publish premiums. The ordinance, the improvement agreement, the bond actually issued and your own lawyer's advice control.

Start here: Contract surety hub · Surety glossary · Surety 101: three parties, one written promise


A US developer who wants to record a map, open lots for sale, or start building houses usually has to promise the city or county that the streets, sewers, water lines, drainage and other public improvements will actually be built. That promise is typically backed by improvement security. When the security is a surety bond, the market often calls it a subdivision bond, a site-improvement bond, or a subdivision performance bond, sometimes paired with a payment bond for labour and materials. It is not a Miller Act contract-performance bond, and it is not a house-buyer's warranty.

This page is the US companion to our surety bonds for Canadian development and subdivision agreements guide. That page already flags California Government Code section 66499 as a statute that lists corporate surety bonds among acceptable improvement security, and notes that the section itself does not prescribe pay-on-demand terms. The walk-through below goes further into Chapter 5 — statutory bond forms, the 50-to-100 percent amount ranges, release clocks and liability limits — and then contrasts Texas county subdivision bonds and Florida's narrower pre-plat building-permit bond.


The short version


What these bonds secure, and what they are not

The usual pattern is simple. A local agency will not record a final map, or will not let lots go to sale, until the developer either finishes the public improvements or posts security so the agency can finish them if the developer does not. The works are the streets, drainage, water, sewer and similar items in the improvement agreement or the approved plans. The obligee is the city, county or other local agency named on the instrument; the principal is the developer or subdivider. If the security is a surety bond, a licensed surety joins that promise. Nearby instruments are easy to confuse with this one.

Instrument Typical obligee What it is for
Subdivision or site-improvement security The city or county The developer's public improvements under a map, plat or improvement agreement
Miller Act / little Miller Act performance and payment bonds The public construction owner, and defined payment-bond claimants Performance of a public construction contract, and unpaid labour and material on that contract
Bid bond or bid guarantee The owner inviting bids The bidder will sign and furnish the required bonds if awarded
Contractor licence bond Often the state licensing agency or the public, as the statute says A licence condition, not map-improvement security
Canadian development-agreement security The municipality Servicing works under a planning or subdivision agreement, often on a demand form

A public-works construction contract on a courthouse or a highway is a different transaction from a developer's obligation to build subdivision streets. The Miller Act and little Miller Act guide is the US statutory map for those contract bonds. A US bid bond is an earlier, tender-stage instrument. Release of subdivision security, when the works are accepted, is a close cousin of the questions in how surety bonds end. A claim still has to follow the issued wording; surety claims basics is the general claims on-ramp, not a substitute for the statute or the bond. The security is also not a house-buyer's warranty. If a statute requires a one-year guarantee of the public improvements after acceptance, as California section 66499.9(c) does, that guarantee runs to the agency under the improvement agreement, not automatically to every homebuyer.


California Chapter 5: forms of security and the statutory bonds

California's Subdivision Map Act — Government Code Division 2 — includes Chapter 5, Improvement Security, sections 66499 through 66499.10, added by Statutes 1974, Chapter 1536. Individual sections have been amended since; the dates appear in the Sources list. The official text was fetched from the California Legislative Information service on November 10, 2026 (PT), section by section. Re-check each section URL before relying on it; a chapter-level display page returned an error that day.

Section 66499(a) says that whenever the division or a local ordinance authorizes or requires security in connection with the performance of any act or agreement, the security "shall be one of the following," with a drafting fork for nonprofit developers described in section 66499.3(c). For a developer who is not that nonprofit, the listed forms are "at the option of and subject to the approval of the local agency." For such a nonprofit, the listed forms are "subject to the approval of the local agency," and section 66499.3(c) then sets special conditions under which that entity need not furnish the ordinary 50-to-100 percent pair.

The five listed forms in section 66499(a) are:

  1. "Bond or bonds by one or more duly authorized corporate sureties."
  2. A deposit, with the local agency or a responsible escrow agent or trust company, at the option of the local agency, of money or negotiable bonds of the kind approved for securing deposits of public moneys.
  3. An instrument of credit from a state, federal or local government agency when any such agency provides at least 20 percent of the financing for the portion of the act or agreement requiring security, or from one or more financial institutions subject to state or federal regulation and pledging that the necessary funds are on deposit and guaranteed for payment, or a letter of credit issued by such a financial institution.
  4. A lien upon the property to be divided, created by contract between the owner and the local agency, if the local agency finds that it would not be in the public interest to require the installation of the required improvement sooner than two years after the recordation of the map.
  5. "Any form of security, including security interests in real property, which is acceptable to the local agency and specified by ordinance thereof."

A contract or security interest used under paragraph (4) or (5) must be recorded. From recordation, a lien attaches with the priority of a judgment lien in an amount necessary to complete the agreed improvements. The agency may later release or subordinate that lien if performance is sufficiently secured by a lien on other property, or if the release or subordination will not jeopardize completion.

Sections 66499.1 and 66499.2 then set out statutory bond forms. They are public statute text, not a private surety's manuscript; this page describes them rather than reprinting the forms in full.

Section 66499.1 is the faithful-performance form, except as provided in section 66499.3. The recitals refer to an agreement with the county board of supervisors or the city council to install and complete designated public improvements, and they incorporate that agreement. The condition is that the principal perform the covenants of the agreement, and any alteration made as provided in it, and indemnify and save harmless the county or city, its officers, agents and employees, as stipulated in the agreement. In addition to the face amount, the form includes costs and reasonable expenses and fees, including reasonable attorney's fees, incurred by the county or city in successfully enforcing the obligation. The surety waives notice of any change, extension of time, alteration or addition, and stipulates that no such change affects its obligations. Appropriate modifications are to be made if the bond is for the performance of an act not provided for by agreement.

Section 66499.2 is the payment-bond form for the security of laborers and material suppliers. Before starting the work, the principal is to file a payment bond to secure the claims referred to in Civil Code Title 3 (commencing with section 9000). The bond runs to the county or city and to the contractors, subcontractors, laborers, material suppliers and other persons referred to in that title, for materials or labour or for amounts due under the Unemployment Insurance Act with respect to the work, and it inures to the benefit of persons entitled to file claims under that title, so as to give them or their assigns a right of action on the bond. It also includes enforcement costs and reasonable attorney's fees incurred by the county or city, and the surety again waives notice of change, extension, alteration or addition. This page does not restate Civil Code Title 3 or the Unemployment Insurance Act. A local agency may use a modified form, or accept a non-bond substitute under section 66499. Compare the issued instrument with the statute.

Section 66499.6 adds that money, a negotiable bond or an instrument of credit deposited as security "shall be a trust fund to guarantee performance and shall not be subject to enforcement of a money judgment by any creditors of the depositor until the obligation secured thereby is performed to the satisfaction of the local agency." Section 66499.10 then distinguishes how a claimant sues: against the holder of a money or negotiable-bond deposit; against the surety, where the security is a surety bond; or against the financial institution, where the security is an instrument of credit.

Unfinished cul-de-sac and vacant lots in a US subdivision, the public works California Chapter 5 security is meant to complete
California Government Code Chapter 5 requires performance and payment security, each in a 50-to-100 percent range, for the agreed public improvements.

California amounts, warranty security and attorneys' fees

Section 66499.3 is the amount statute. Security to guarantee the performance of any act or agreement "shall be in the following amounts":

Component in § 66499.3 Amount the legislative body determines What it secures
Faithful performance, subd. (a) Not less than 50 percent nor more than 100 percent of the total estimated cost of the improvement or of the act to be performed Performance of the act or agreement
Payment, subd. (b) An additional amount, not less than 50 percent nor more than 100 percent of that same estimated cost Payment to the contractor, subcontractors, and persons furnishing labour, materials or equipment to them
Guarantee and warranty, subd. (d) An amount the legislative body determines is necessary, "subject to the limitations of Section 66499.9" Guarantee and warranty of the work for one year after completion and acceptance, against defective work, labour or materials
Diagram of California Chapter 5 subdivision security: a faithful-performance bond and an additional payment bond, each in a 50 to 100 percent range, plus a one-year warranty set-aside subject to section 66499.9

The performance and payment figures are each a range, not a single statewide percentage. The legislative body — the city council or county board — sets the number inside that range.

Subdivision (c) is a special path for a California nonprofit corporation funded by the United States or one of its agencies, or by this state or one of its agencies. If the listed conditions are met — including a letter of credit for 100 percent of the contract of improvements, or contractor bonds running to the nonprofit and the local agency as co-obligees, plus a depository and progress-payment regime — that entity "shall not be required to comply with subdivisions (a) and (b)." Read section 66499.3(c) in full if that path may apply.

Section 66499.4 restates a rule that also appears in the statutory bond forms: as part of the obligation, and in addition to the face amount, there shall be included costs and reasonable expenses and fees, including reasonable attorneys' fees, incurred by the local agency in successfully enforcing the obligation secured. Section 66499.5 is a narrow offset: if the improvements are financed and installed under special assessment proceedings, the local agency may provide by ordinance that, once the contractor furnishes the bonds required by the assessment act being used, the subdivider's improvement security may be reduced by a corresponding amount.


California release, reduction and the limits on liability

Section 66499.7 is the release and reduction statute. It was amended by Statutes 2015, Chapter 269 (SB 184), effective January 1, 2016. The security "shall be released in whole or in part" in the manner the section then sets out.

Faithful-performance security shall be released upon the performance of the act or final completion and acceptance of the required work. The legislative body may provide for partial release as work is accepted, consistent with the section. If the security is documentary evidence such as a surety bond or a letter of credit, the legislative body shall release it and return the original to the issuer upon performance of the act or final completion and acceptance. If it cannot return the original, the security shall be released by written notice sent by certified mail to the subdivider and the issuer within 30 days of acceptance of the work. That notice must state that the work has been performed or completed and accepted, describe the project, and carry the notarized signature of the agency's authorized representative.

The section then sets a review sequence that uses several 45-day clocks. When the subdivider believes the obligation is complete, it may notify the local agency in writing, including a list of work completed. The agency has 45 days to review and comment or approve, and, if it does not agree that all work has been completed in accordance with the plans and specifications, to supply a list of remaining work. Within 45 days of receiving that list, the subdivider may provide cost estimates for the remaining work; the agency then has 45 days to review, comment, and approve, modify or disapprove those estimates. The agency is not required to use this partial-release process more than once between the start of work and completion and acceptance of all work, though it may allow a partial release earlier.

If the agency approves the cost estimate, it shall release all performance security except for security of up to 200 percent of the remaining-work estimate. That process occurs when the remaining-work estimate does not exceed 20 percent of the total original performance security, unless the agency allows a release earlier. Substitute security may be used, subject to approval; a release is not effective until the agency receives and approves the replacement. A reduction under the section is not an acceptance of the completed improvements, and the risk of loss or damage, and the obligation to maintain the improvements, remain the subdivider's until the public improvements have been accepted and the other required improvements have been fully completed. Upon completion, the agency shall notify the subdivider, or the subdivider's assigns, in writing within 45 days. Within 45 days of that notification, release of any remaining performance security shall be placed on the legislative body's agenda, unless authority has been delegated, in which case any remaining performance security shall be released within 60 days of the written statement of completion.

Payment security is on a different clock. After passage of the time within which claims of lien are required to be recorded under Civil Code Article 2 (commencing with Section 8410) of Chapter 4 of Title 2 of Part 6 of Division 4, and after acceptance of the work, the payment security shall be reduced to the total claimed by all claimants for whom claims of lien have been recorded and notice given in writing to the legislative body. If no claims have been recorded, the payment security shall be released in full.

The release shall not apply to any required guarantee and warranty period required by section 66499.9, nor to the amount the local agency deems necessary for that period, nor to costs and reasonable expenses and fees, including reasonable attorney's fees. The legislative body may authorize public officers or employees to release or reduce security in accordance with the section and with any rules it prescribes.

Section 66499.8 adds a coordination rule. Where performance of the obligation is subject to the approval of another agency, the local agency shall not release the security until the obligation is performed to that other agency's satisfaction. The other agency has two months after completion to register satisfaction or dissatisfaction; if it has not done so at the end of that period, it shall be conclusively deemed that the performance was done to its satisfaction.

Section 66499.9 then limits liability on the faithful-performance security to four items: (a) performance of the work covered by the agreement, or performance of the required act; (b) performance of any changes or alterations in that work, "provided, that all such changes or alterations do not exceed 10 percent of the original estimated cost of the improvement"; (c) the guarantee and warranty of the work, for one year following completion and acceptance, against defective work, labour or materials; and (d) costs and reasonable expenses and fees, including reasonable attorneys' fees. The one-year warranty in section 66499.3(d) is expressly "subject to" this section. Whether a change order sits inside or outside the 10 percent cap has to be measured against "the original estimated cost of the improvement," with the issued agreement and counsel.

A public owner's desk that is accepting or reducing these instruments will also want the verification habits in our public owner's guide to accepting and verifying bonds.


Texas county subdivision bonds under Chapter 232

Texas Local Government Code Chapter 232 regulates subdivision platting in the county setting described in that chapter. The official text was fetched on November 10, 2026 (PT) from the Texas Constitution and Statutes resource. This page addresses the bond provisions in Subchapter A. It does not survey municipal subdivision regulation under other Texas chapters, and it does not walk the additional infrastructure-bond rules in Subchapter B (counties near an international border), including section 232.027.

Under section 232.003, a commissioners court may, by an order adopted and entered in its minutes after published notice, adopt listed subdivision requirements. Item (7) is that the court may require the owner of the tract to be subdivided to execute a good and sufficient bond in the manner provided by section 232.004. Section 232.002(a) then gives the requirement teeth: the court may refuse to approve a plat if any bond required under the chapter is not filed with the county.

Section 232.004, "Bond Requirements," says that if the commissioners court requires the owner to execute a bond, the owner must do so "before subdividing the tract unless an alternative financial guarantee is provided under Section 232.0045." The bond must:

  1. be payable to the county judge of the county in which the subdivision will be located, or to the judge's successors in office;
  2. be in an amount determined by the commissioners court to be adequate to ensure proper construction of the roads and streets in and drainage requirements for the subdivision, "but not to exceed the estimated cost of construction of the roads, streets, and drainage requirements";
  3. be executed with sureties as may be approved by the court;
  4. be executed by a company authorized to do business as a surety in the state, if the court requires a surety bond executed by a corporate surety; and
  5. be conditioned that the roads and streets and the drainage requirements will be constructed in accordance with the specifications adopted by the court, and within a reasonable time set by the court.

Two contrasts with California are immediate. The Texas county amount is capped at the estimated cost; it is not a 50-to-100 percent pair of performance and payment bonds. And section 232.004 as fetched is a construction bond for roads, streets and drainage; it does not, in the text reviewed, set out a separate statutory payment-bond form the way California section 66499.2 does.

Section 232.0045 is the in-lieu list. "In lieu of the bond an owner may deposit cash, a letter of credit issued by a federally insured financial institution, or other acceptable financial guarantee." If a letter of credit is used, it must list as the sole beneficiary the county judge of the county in which the subdivision is located, and be conditioned that the owner will construct any roads or streets in the subdivision in accordance with the court's specifications and within a reasonable time set by the court. The letter-of-credit conditions in section 232.0045(b), as fetched, name "roads or streets" and do not repeat the "drainage requirements" clause that appears in section 232.004(5). Do not assume the two instruments are worded identically; read the instrument the court actually accepted.

Chapter 232 has been amended in recent sessions, including in 2023 and, for some other sections, in 2025. The bond sections walked above carry older amendment lines in the official text fetched November 10, 2026 (section 232.004, last listed amendment 1999; section 232.0045, added 1989). Re-check the live chapter before relying on a cap, an obligee name or an in-lieu form.

Rural subdivision road and corrugated drainage culvert, the kind of county work a Texas Chapter 232 bond may secure
Under Texas Local Government Code section 232.004, a county bond is capped at the estimated cost of the roads, streets and drainage.

Florida's pre-plat building-permit bond under section 177.073

Florida Statutes section 177.073 is titled "Expedited approval of residential building permits before a final plat is recorded." The 2026 official compilation on the Florida Senate's statutes site lists the history as section 1, chapter 2024-210; section 14, chapter 2025-6; and section 5, chapter 2026-64. It is a building-permit timing statute, not a general Florida subdivision-improvement security code; local Florida subdivision regulations that also require improvement security are not surveyed here. Covered governing bodies — described in section 177.073(2) by population and, for municipalities, by a contiguous-land and future-land-use condition, with a stated exception for a county subject to section 380.0552 — must maintain a program to expedite those pre-plat residential permits. The program's percentage caps and a December 31, 2027 update are in subsection (2); this page does not restyle those planning rules as bond law.

The bond sits in subsection (6). The governing body must issue the number or percentage of building permits the applicant requests, in accordance with the Florida Building Code and the section, "provided the residential buildings or structures are unoccupied and all of the following conditions are met":

Section 177.031(9) defines "Improvements" — not the words "necessary improvements" as a separate defined term — and says they may include, but are not limited to, street pavements, curbs and gutters, sidewalks, alley and walkway pavements, water mains, sanitary sewers, storm sewers or drains, street names, signs, landscaping, permanent reference monuments, permanent control points, monuments, or any other improvement required by a governing body. Section 177.073(6)(c) then uses the phrase "necessary improvements, as defined in s. 177.031(9)." This page does not invent a tighter definition than that cross-reference, and it does not restate section 163.3202(5)(b).

Three limits follow from the text. First, the 130 percent figure is a ceiling on this particular bond ("for up to 130 percent"), tied to incomplete improvements at the time of the application, not a general Florida penal-sum rule for every subdivision. Second, the local government may waive the requirement, through its program or case by case. Third, later subsections restrict sale and occupancy — an applicant may contract to sell but may not transfer ownership, and may not obtain a temporary or final certificate of occupancy, until the final plat is approved and recorded — and subsection (10) requires the applicant to indemnify the local government. That indemnification runs from the applicant; it is not a surety bond. Do not treat section 177.073 as if it were California Chapter 5. It does not, in the text reviewed, set a statutory payment-bond form, a 50-to-100 percent pair, or a 45-day release sequence. It is a waivable condition of a pre-plat residential building-permit program.


A practical checklist

General education, not legal advice. Use it as a list of questions for the agency's bond desk, the developer's engineer and counsel, and the surety professional.

When the map or plat is still in review

  1. Identify the statute, ordinance and improvement agreement that actually apply (California Chapter 5, a Texas county order under Chapter 232, a Florida 177.073 program, or another local regime this page does not cover).
  2. Name the obligee exactly — the city, the county, or, in the Texas county statute, the county judge — and confirm whether both performance and payment security are required.
  3. Confirm the amount or percentage against the agency's estimate of the cost of the improvements, including any warranty holdback; do not assume a 50, 100 or 130 percent figure applies unless the governing text says so.
  4. If the agency will accept cash, a letter of credit or another substitute, compare those terms with the bond, including the beneficiary and the release mechanics.

When the bond is issued or a substitute is posted

  1. Compare the issued performance and payment forms with any statutory form (in California, sections 66499.1 and 66499.2) and with the improvement agreement they incorporate.
  2. Check notice-waiver, attorneys'-fees and change-order language against the statute and the agreement, including California's 10 percent change cap in section 66499.9(b).
  3. Diary any warranty period that will survive substantial completion — in California, one year after completion and acceptance, subject to section 66499.9.
  4. Keep the original documentary evidence where it can be returned to the issuer on release, and record how the agency prefers to give written release if the original cannot be returned.

When the works are finishing and security should come off

  1. On a California Chapter 5 job, follow the written-notice and 45-day review sequence in section 66499.7 before assuming a reduction or a return of the original is due; a partial reduction is not itself acceptance of the improvements.
  2. Treat payment security on its own clock, including any mechanic's-lien claim period the statute incorporates.
  3. Do not treat a warranty or guarantee set-aside as released merely because performance security for the original works has been reduced.
  4. If another agency must also accept the work, add that agency's satisfaction rule (in California, the two-month rule in section 66499.8) to the diary.

What to verify at the source


FAQs

What is a subdivision or site-improvement bond? It is improvement security, often a surety bond, that a developer posts with a city or county so that promised public improvements — streets, drainage, utilities and similar works — will be completed if the developer does not complete them. Some statutes also require a companion payment bond for labour and material. The obligee is the local agency, not the lot purchaser.

Is a subdivision bond the same as a Miller Act performance bond? No. A Miller Act or little Miller Act performance bond secures a contractor's public construction contract. A subdivision or site-improvement bond typically secures a developer's improvement obligations under a map, plat or improvement agreement. The forms, claimants and statutes are different.

Does every US city require a 100 percent subdivision bond? No. California section 66499.3 lets the legislative body set faithful-performance security and payment security each at 50 to 100 percent of the estimated cost. Texas section 232.004 caps a county bond at the estimated cost of the roads, streets and drainage. Florida section 177.073(6)(c) uses a different figure — a performance bond for up to 130 percent of incomplete necessary improvements — in a pre-plat permit program the local government may waive. Always read the text that governs the job.

Can a developer post cash or a letter of credit instead of a surety bond? Often, if the governing statute or ordinance allows it. California section 66499 lists several non-bond forms, subject to local-agency approval. Texas section 232.0045 expressly allows cash, a letter of credit from a federally insured institution, or another acceptable financial guarantee in lieu of the Chapter 232 bond. The substitute has its own beneficiary, conditions and release path.

When does California require the agency to return a subdivision bond? Section 66499.7 releases faithful-performance security upon performance of the act or final completion and acceptance, with a partial-reduction path that uses 45-day review clocks, a remaining-work threshold of 20 percent of the original performance security, and a residual of up to 200 percent of the remaining-work estimate. The original documentary evidence is to be returned, or a specified certified-mail release sent, when the work is accepted. Payment security and warranty set-asides follow different rules, and a reduction is not itself acceptance.

Does Florida section 177.073 replace a city's ordinary subdivision-improvement bond? The section, as fetched, is a condition of a program for issuing residential building permits before a final plat is recorded. It requires a valid performance bond for up to 130 percent of incomplete necessary improvements, unless the local government waives it. It does not, in the text reviewed, repeal other local improvement-security requirements. Confirm both the 177.073 program and any local subdivision rules that still apply.


Sources

Retrieved November 10, 2026 (PT).

  1. California Government Code § 66499 (forms of improvement security). leginfo.legislature.ca.gov
  2. California Government Code § 66499.1 (statutory faithful-performance bond form). leginfo.legislature.ca.gov
  3. California Government Code § 66499.2 (statutory payment bond form; Civil Code Title 3 commencing with § 9000). leginfo.legislature.ca.gov
  4. California Government Code § 66499.3 (amount ranges; nonprofit path; one-year warranty security). leginfo.legislature.ca.gov
  5. California Government Code § 66499.4 (costs and reasonable attorneys' fees in addition to the face amount). leginfo.legislature.ca.gov
  6. California Government Code § 66499.5 (reduction where improvements are installed under special assessment proceedings). leginfo.legislature.ca.gov
  7. California Government Code § 66499.6 (deposited money, negotiable bonds or instruments of credit held as a trust fund). leginfo.legislature.ca.gov
  8. California Government Code § 66499.7 (release and partial reduction, including 45-day clocks; amended Stats. 2015, ch. 269). leginfo.legislature.ca.gov
  9. California Government Code § 66499.8 (release where another agency must also be satisfied; two-month rule). leginfo.legislature.ca.gov
  10. California Government Code § 66499.9 (limits on faithful-performance liability, including the 10 percent change cap and the one-year warranty). leginfo.legislature.ca.gov
  11. California Government Code § 66499.10 (who may be sued, depending on the form of security). leginfo.legislature.ca.gov
  12. Texas Local Government Code Chapter 232, especially §§ 232.002, 232.003(7), 232.004 and 232.0045 (Texas Constitution and Statutes official text). tcss.legis.texas.gov
  13. Florida Statutes § 177.073 (2026 compilation; expedited residential building permits before a final plat is recorded; performance-bond condition in subsection (6)(c)). flsenate.gov
  14. Florida Statutes § 177.031(9) (2026 compilation; definition of "Improvements"). flsenate.gov
  15. Florida Statutes § 163.3202(5)(b)2. (2026 compilation; definition of "planned unit development" or "master planned community," the cross-reference used by § 177.073(6)(c)). flsenate.gov
  16. California Civil Code § 8410 (preliminary-notice condition; starts Article 2 of Chapter 4 of Title 2 of Part 6 of Division 4, the article cited by Gov. Code § 66499.7(h) for the lien-recording period). leginfo.legislature.ca.gov