How Australian construction performance security works: retention money and performance bonds, including bank guarantees and insurance bonds, and the statutory release, substitution and notice-before-recourse rules now in force in Victoria and Western Australia.
Education only / verify at source / not legal advice. This guide explains how construction performance security is treated in two current Australian statutes we opened on November 15, 2026 (PT): Victoria's Building and Construction Industry Security of Payment Act 2002, authorised version 015 as at 24 June 2026, and Western Australia's Building and Construction Industry (Security of Payment) Act 2021, official version as at 21 October 2026. Every rule cited comes from a public source retrieved that day, listed at the end. Australia is a federation. The statute that governs a particular contract may be a different State's or Territory's Act, or an earlier version of the same Act. Global Guarantors publishes industry education. We aren't a surety, bank, insurer, government agency or law firm, and we don't publish premiums or guarantee fees. The construction contract, the instrument, the statute that applies, and your own lawyer's advice control.
Start here: Contract surety hub · Surety 101: three parties, one written promise · Surety in Germany: Bürgschaften and VOB/B performance security
A North American contractor who wins work in Australia often expects to post a performance bond and a payment bond, in the sense used on a Miller Act or little-Miller-Act job. What the contract usually asks for looks different. Security for the contractor's performance is commonly given as retention money, or as a performance bond — a legally binding instrument that may be described as a bond, a guarantee or an unconditional undertaking, often issued by a bank and, in at least one statute we opened, also issuable by an insurer authorised under the Insurance Act 1973 (Commonwealth).
That instrument is not a labor-and-material payment bond for unpaid subcontractors and suppliers. It is security for performance obligations under the construction contract. Two Australian security-of-payment statutes, in the versions we opened, also give statutory rights about when a performance security must be released and when a party may have recourse to it, and, in Western Australia, when retention money must be held on trust and when a compliant performance bond may be substituted for retention.
Those rights are not uniform. Victoria's 2002 Act, as amended by the Building Legislation Amendment (Fairer Payments on Jobsites and Other Matters) Act 2025 (No. 43/2025), now provides for progress payments "and the release of performance securities." Western Australia's 2021 Act has its own Division on performance security and a separate Part on retention money trusts. This page walks those two statutes, adds short notes on New South Wales, Queensland and South Australia, and is not a survey of every State and Territory.
Both statutes define "performance security" as retention money or a performance bond. They do not use that term to mean a Miller Act payment bond, and they do not treat a performance bond as a substitute for the statutory progress-payment and adjudication machinery.
In the Victorian Act, as authorised in version 015, "performance bond" means "a security issued to or executed in favour of a party to a construction contract to secure the performance by another party of obligations under the contract and includes — (a) a guarantee; and (b) a bond." "Performance security" means a performance bond or retention money. "Release," in relation to a performance security, means the return or cancellation of a performance bond, or, in the case of retention money, payment of the money to the party who carried out the construction work or supplied the related goods and services. "Retention money" is defined, inclusive of GST, as money retained out of money payable under the contract, or paid to a party and retained, as security for the other party's performance of those obligations.
In the Western Australian Act, official version as at 21 October 2026, the Division 6 definitions are in section 56. A "performance bond" means "a legally binding instrument (whether described as a bond, guarantee or otherwise) issued by an authorised issuing institution to pay a party to a construction contract named in the instrument an amount of money up to a specified limit on demand by that party, as security for the performance of obligations under the contract of another party to the contract." "Performance security" again means retention money or a performance bond. "Recourse," for a performance bond, means the person named in the bond demanding and receiving payment under the bond; for retention money, it means the person who retains the money taking the money for themselves. "Release" is the return or cancellation of a performance bond, or payment of retention money, in the terms that section uses.
Those definitions are the place to start. An instrument may be labeled an unconditional undertaking, a bank guarantee, an insurance bond or a surety bond; whether it is a "performance bond" for the Act that applies depends on that Act and the instrument, not the label.
It is not, on the face of these sections, a payment bond for unpaid subcontractors and suppliers in the sense described in our Miller Act and little Miller Act guide. Unpaid parties in Australia more often look to the security-of-payment claim and adjudication path in the applicable Act, and to whatever contractual or statutory trust, charge or other protection that Act or another statute gives them.
Standard-form Australian construction contracts, including Australian Standard forms, commonly deal with security, retention and release in their own clauses. Those forms are copyrighted publications. This page does not reproduce them. The edition and amendments that were incorporated into the particular contract, and any special conditions, are the text to use, read against the statute that applies.
Western Australia's definition is the clearer official statement of who may issue a performance bond for the purposes of that Act. An "authorised issuing institution" means a "recognised financial institution" or "a person authorised under the Insurance Act 1973 (Commonwealth) to carry on insurance business in Australia." A recognised financial institution, in the same Act, means an authorised deposit-taking institution as defined in section 5(1) of the Banking Act 1959 (Commonwealth), or any other body prescribed by the regulations for the purposes of that definition.
The Western Australian statute therefore treats a performance bond as an on-demand instrument issued either by a bank (or another prescribed body) or by an authorised insurer. This page does not treat market labels as statutory terms, and it does not rate, name or recommend any bank or insurer.
Section 60 of the Western Australian Act then sets out when a performance bond is a "compliant performance bond" for the specific purpose of substituting the bond for retention money under section 59. Among other things, the bond must be unconditional; it must not expire and must be wholly irrevocable; the amount payable must be not less than the retention money to be released, and in the same currency; unless the contract provides otherwise, the applicable law and courts must be those of Western Australia; the bond must identify the party who may demand and receive payment, and the authorised issuing institution, including its Australian Business Number and its Australian Company Number or Australian Registered Body Number; the times for release of performance security under the contract must be maintained; and the credit rating of the authorised issuing institution must satisfy any minimum credit rating requirement prescribed by the regulations, together with any other prescribed requirements. The Building and Construction Industry (Security of Payment) Regulations 2022 (WA), official version as at 1 July 2026, set that minimum in regulation 10: "the rating of A under the Standard & Poor's Long-Term Issuer Credit Ratings," or, "if the construction contract provides for a lower minimum credit rating — that lower minimum credit rating." Regulations change; check the current version.
The Victorian definition of "performance bond" includes a guarantee and a bond, but it does not, in the definition we opened, name the class of issuer. Who is an acceptable issuer on a Victorian project is therefore a matter for the contract, any applicable regulations, and counsel, not a gap this page fills with market practice.
The leading High Court case on these instruments is Wood Hall Ltd v Pipeline Authority [1979] HCA 21; (1979) 141 CLR 443, where bank "guarantees" had been given in place of cash security and retention on a pipeline contract. The appeal was dismissed. Gibbs J (with whom Mason J agreed) held that reading the undertakings as conditional on a demand the building contract permitted "would of course be quite inconsistent with the express statement in the bank guarantees that the undertaking of the Bank is unconditional" (at 451). Stephen J wrote: "Only so long as it is 'as good as cash' can it fulfil its useful purpose" (at 457–458). Barwick CJ called the label "guarantee" "a complete misnomer," saying the bank's relationship "has, in my opinion, none of the elements of suretyship" (at 445). Later cases deal with exceptions, such as restraining a call that breaches the contract; this page does not survey them. Our page on surety bonds versus letters of credit discusses the general contrast with suretyship.
The Western Australian definition makes no distinction between a bank-issued and an insurer-issued performance bond: both are instruments to pay a named party up to a specified limit "on demand." Whether a particular insurance bond is drafted as an on-demand undertaking or as a conditional, suretyship-style promise depends on its wording. Our page on surety versus insurance is a general primer; it does not decide how a particular Australian instrument will be characterized.
Act No. 43/2025 received assent on 13 November 2025; the endnotes to authorised version 015 record that the amending provisions for the 2002 Act commenced on 15 April 2026. The main purpose of the 2002 Act, as so amended, is "to provide for entitlements to progress payments and the release of performance securities" for persons who carry out construction work or supply related goods and services under construction contracts. The object in section 3 now includes an entitlement to the release of a performance security, and the means of recovery now include serving a performance security claim, serving a performance security schedule, and the release of the whole or part of a performance security determined by an adjudicator.
Section 17A allows a person referred to in section 9(2) who is or who claims to be entitled to the release of the whole or a part of a performance security to serve a claim on the person who, under the construction contract, is or may be liable to release it. The claim must be in the prescribed form (if any), identify the construction work or related goods and services, specify the type and amount of performance security claimed, state that it is made under the Act, and contain any other prescribed information. The claimant's entitlement to serve the claim is not affected by the termination, purported termination or expiry of the construction contract.
Section 17B sets the earliest time a performance security claim may be served: no earlier than the earliest of a day that is at least 20 business days after the end of the relevant defects liability period for the work or supply to which the security relates, or on or after a day, or the day of an event, specified in the construction contract. A claim served before that earliest day is not invalid; it is taken to be served on the earliest day, and the time for a performance security schedule does not arise until then. Section 17C sets the latest time: no later than the latest of the day (if any) determined under the contract as the latest day, or the last day of the named month following the named month in which the last defects liability period set out in the contract (if any) ends. Section 17D provides that a contract provision has no effect to the extent that it purports to override the right to serve a claim under section 17A, to set an earlier earliest day than section 17B, or to set a later latest day than section 17C.
Section 17E then deals with the respondent's performance security schedule. The respondent may serve a schedule, which must identify the performance security, identify the amount proposed to be released if it is not the claimed amount, indicate when the respondent proposes to release the security or any part of it, and be in the prescribed form and contain the prescribed information, if any. If the respondent proposes to release less than the claimed amount, the schedule must say why. Section 17E(4) is the default: the respondent becomes liable to release the claimed amount on the due date for release if a claim for that amount is served and the respondent does not serve a schedule within whichever of the contract time or 10 business days after the claim is served expires earlier. Section 17F then applies if that liability arises and the respondent fails to release on the due date. The claimant may apply to a court of competent jurisdiction for an order that the respondent must release the security, or may make an adjudication application under section 18A(1). In those court proceedings, judgment is not to be given unless the court is satisfied of the circumstances in section 17F(1), and the respondent is not entitled to bring a cross-claim or to raise a defense in relation to matters arising under the construction contract. Section 17G gives the same court and adjudication options where the respondent served a schedule on time proposing to release the whole or part of the security, but then fails to release that amount by the due date, with the same limits on cross-claims and defences in court.
The due date for release is in section 12(1A). A performance security is due to be released on the day on which it must be released under the contract or, if the contract does not expressly provide for when it must be released, on the day that is 10 business days after the earliest day on which a performance security claim may be served under section 17B(1). Section 12(1B) then cuts late contract dates: a term has no effect to the extent that it provides for the release of a performance security later than the day that is 20 business days after a performance security claim is served. Section 12(3) addresses interest on the unpaid amount of a performance security that has become due to be released, at the greater of the rate for the time being fixed under section 2 of the Penalty Interest Rates Act 1983 or the rate specified under the construction contract. This page does not state a current interest rate.
Recourse is separately constrained. Section 17H provides that a party to a construction contract is not entitled to have recourse to the whole or a part of a performance security unless the party has served the party who provided the security with a notice of intention to have recourse, and at least five business days have passed since that notice was served, or a longer period if the contract provides for one. The notice must be in writing in the prescribed form (if any), identify the contract and the provisions relied on, state the amount if recourse is to only part of the security, and "describe the circumstances that entitle the party to have recourse." Section 17H(3) makes these requirements part of every construction contract, despite any provision that purports to override them.
On timing, section 54(1) says the Act as amended "applies in respect of a construction contract that is entered into before, on or after the commencement" of the amendments, subject to the rest of section 54, which preserves the old rules for payment claims and adjudication applications already on foot. Read section 54 before assuming which version governs a step.
Western Australia's Building and Construction Industry (Security of Payment) Act 2021, official version as at 21 October 2026 (PCO suffix 00-f0-00), is a different statute. The Western Australian Government's Building and Energy page says the Act "applies to construction contracts entered into on or after 1 August 2022." The official compilation table shows that commencement was staged, and section 9(1) applies each provision only to contracts "entered into after the provision comes into operation." Most of the Act commenced on 1 August 2022; section 57 (notice before recourse) and Part 4 (retention trusts, other than section 87) on 1 February 2023; and sections 59 to 61 (substitution) on 1 February 2024. The official Act itself, in section 3, describes its object as providing an effective and fair process for securing payments, achieved primarily by a statutory entitlement to progress payments, an expedited claims and adjudication procedure, ensuring money is held on trust if it has been retained to secure performance, and giving other statutory entitlements, "including the right to suspend work or supply if not paid and to access retained money by substituting a performance bond."
Notice before recourse is in section 57. A party is not entitled to have recourse to performance security unless the party has given the other party written notice of the intention to have recourse, in the approved form (if any), and at least five business days have passed, or a longer period if the contract provides one. The notice must identify the construction contract and the provisions the party relies on to have recourse; the rest of the content list is in the section.
Section 58 is the release right. Among other things, it deals with release of performance security to which a progress payment relates, and with release that may be sought or required in the circumstances the section describes, including through an adjudication determination. The exact triggers are in the official text; this page does not collapse them into a single release date.
Section 59 is the substitution right that North American readers, used to retention held by the owner, often miss. Subsection (1) states that a party to a construction contract "is entitled to the release of retention money under the contract by substituting a performance bond for the retention money in accordance with this section." A claimant may seek that substitution in a payment claim for a progress payment, may substitute several separate performance bonds for a single amount of retention, and may seek a later release of further retention by substituting further bonds. A payment claim that seeks the substitution must identify the construction contract, indicate the amount of retention money to be released, state that it is made under the Act, and be accompanied by a draft of the compliant performance bond, or of each such bond, "in final form except for its execution by the authorised issuing institution," together with any other information the regulations require. An adjudicator's determination may require the substitution proposed in the payment claim. Section 60, already summarized above, is the compliance list for that bond, including that it is unconditional, does not expire, and is wholly irrevocable.
Retention money trusts are a separate Part 4. Section 71 provides that retention money under a construction contract to which the Part applies is, by the operation of that section, held on trust by the party who retains the money from the retention money trust commencement date until the retention money trust end date. Until the money is paid into a retention money trust account, the trust applies to the property of the party who retains the money, but only to the extent of the amount of the retention money. While the money is held on trust, it is not available for payment to a third-party creditor of any of the parties, and it is not liable to be attached or taken in execution for satisfying a monetary judgment entered in favor of such a creditor, in the terms section 71 uses.
That trust does not apply to every Western Australian construction contract. Section 70 applies the Part to a construction contract to which the Act applies, except if the party for whom the work is carried out, or to whom related goods and services are supplied, is a government party; or if the value of the contract at the time it is first entered into, and at any later time following a variation or of estimates used to value the contract, does not exceed the amount prescribed by the regulations (the prescribed retention money threshold); or if the contract is for home building work of a kind excluded by section 70(2); or if the contract is of a kind excluded by the regulations. Regulation 11 of the 2022 Regulations sets the prescribed retention money threshold at $1,000,000 for contracts entered into on or after 1 February 2023 and before 1 February 2024, and $20,000 for contracts entered into on or after 1 February 2024.
The rest of Part 4 is operational. Section 74 requires the retaining party to pay the money into a retention money trust account with a recognised financial institution, established within 10 business days after the contract is entered into (or earlier, where the money is paid separately as security). Section 73 requires drawing down an available debt facility if necessary. Section 83 says the trusts "have effect despite anything to the contrary in a construction contract or any other contract." Withdrawals, records, interest and offences are in sections 76 to 87.
The table compares only the two official texts walked above.
| Topic | Victoria (authorised v. 015, as at 24 June 2026) | Western Australia (official, as at 21 Oct 2026) |
|---|---|---|
| What "performance security" includes | A performance bond or retention money. A performance bond includes a guarantee and a bond. | Retention money or a performance bond issued by an authorised issuing institution (a recognised financial institution or an insurer authorised under the Insurance Act 1973 (Cth)). |
| Notice before recourse | Section 17H: written notice, then at least 5 business days, or a longer period the contract provides. | Section 57: written notice in the approved form (if any), then at least 5 business days, or a longer period the contract provides. |
| Statutory path to release | A performance security claim under section 17A, with earliest and latest times in sections 17B and 17C, and a due-date rule in section 12. | Release rights in section 58, including in connection with progress payments and adjudication, as that section provides. |
| Substituting a bond for retention | Not described in the Victorian definition or claim sections summarized above as a statutory substitution right of the Western Australian kind. Do not assume a parallel right. | Sections 59 and 60 (contracts from 1 Feb 2024): a claimant may seek to substitute a compliant, unconditional, irrevocable performance bond for retention money. |
| Retention money held on trust | Not a feature we extracted from the Victorian provisions walked on this page. Do not assume a Western Australian-style statutory trust. | Part 4, including section 71, for contracts to which the Part applies; government parties, contracts at or below the prescribed threshold, and other statutory exclusions sit in section 70. |
The 5-business-day notice period appears in both statutes, and both allow a longer contractual period. That is a feature of two current texts, not a national rule.
Security of payment in Australia is State and Territory legislation, not a single Commonwealth construction-bond statute. Three short notes, kept narrow on purpose:
Readers with a contract in any of these States, or in Tasmania, the Australian Capital Territory or the Northern Territory, should open the current official statute and not assume that the Victorian or Western Australian model applies.
The construction contract still matters. Statutory rights sit alongside, and in described respects override, contract terms, and due dates, defects-liability periods, bond forms and issuer requirements are often in the special conditions. Australian Standard and other published forms are copyrighted; use the signed contract. Our pages on how surety bonds end and on surety claims basics discuss release, cancellation and claims in general terms. They do not displace section 17H or section 57, and they do not tell a reader whether a particular Australian instrument may be called.
Other countries' performance-security models are useful only as contrast, not as a source of Australian law. Germany's accessory Bürgschaft and first-demand practice are walked in our Germany page, already linked above. France's retention and payment-guarantee practice is walked in our France surety and retention page.
For a contractor posting security on an Australian job
For an owner or head contractor holding security
For a surety, insurer or bank asked to issue the instrument
Is an Australian performance bond the same as a US performance bond or a Miller Act payment bond? Not on the face of the Victorian and Western Australian statutes. There, a performance bond is security for performance, grouped with retention money as "performance security," not a labor-and-material payment bond.
Can an insurance company issue the security, or only a bank? In Western Australia, yes: an authorised issuing institution includes an authorised deposit-taking institution (or another prescribed body) and a person authorised under the Insurance Act 1973 (Cth). The Victorian definition does not name an issuer class. The contract may be narrower than the statute.
How much notice is required before a call on the security? In Victoria (section 17H) and Western Australia (section 57), written notice and at least five business days, or a longer contractual period. That is not a national rule.
Can retention money be replaced with a bond? In Western Australia, sections 59 and 60 let a claimant seek to substitute a compliant performance bond for retention money, for contracts entered into on or after 1 February 2024. We found no parallel Victorian right. Elsewhere, read the contract and the local Act.
When does Victoria allow a claim for release of a performance security? Section 17B sets an earliest day (20 business days after the end of the relevant defects liability period, or a day or event the contract specifies, whichever is earliest), section 17C a latest day, and section 12 the due date for release, with a 20-business-day cap on later contract dates after a claim is served.
Does Western Australia require retention money to be held on trust? Yes, where Part 4 applies (section 71). Section 70 excludes government-party contracts, contracts not exceeding the prescribed threshold ($20,000 for contracts entered into on or after 1 February 2024, under regulation 11), certain home building work and contracts excluded by the regulations.
All sources below were retrieved on November 15, 2026 (PT). Dates in parentheses are the dates those documents themselves bear, where they bear one.