UK Commercial Payments Bill: cash retention ban and surety alternatives
What cash retention is, what the Bill proposes, how performance / retention / warranty bonds are discussed as alternatives, and what to watch next.
UK Commercial Payments Bill: cash retention ban and surety alternatives
Published: October 1, 2026 · Updated: October 28, 2026 · Last verified: October 28, 2026 (PT)
Education only / verify at source / not legal or placement advice. This page explains a UK Bill that is still before Parliament, not a finished statute. Parliamentary text, stage and commencement rules can change. Global Guarantors publishes educational reference, not premiums, quotes, brokerage, lobbying or legal advice. Confirm the live Bill page, Hansard, the current print of the Bill and licensed UK counsel before you rely on anything here.
UK ban: where it standsLast updated: October 28, 2026 (PT)
What it is: The Commercial Payments Bill [HL] is a Government Bill. It is pending legislation, not law.
Stage reached: Passed the House of Lords. Third Reading was on 20 October 2026, and the Bill was sent to the House of Commons. At Third Reading the Lords made only a privilege amendment, so the construction retention ban went to the Commons in the form agreed at Lords Report. Commons First Reading: 21 October 2026, printed as Bill 166.
Next stage: Commons Second Reading (not yet scheduled as of October 28, 2026), then Committee, Report and Third Reading. If the Commons changes the Bill, the Lords must consider those changes. Royal Assent comes after that.
What the Bill would do on retention: It would amend the Housing Grants, Construction and Regeneration Act 1996 so that cash retention clauses in construction contracts become ineffective and are then banned (void), with statutory return of sums still held.
Start date: None set. The Bill leaves commencement to regulations made by the Secretary of State, and the Government has said it will consult further on implementation timing.
Still open: Commons amendments. These include a possible return of the resident management company exemption, which was debated at Lords Report and not pressed. Also open: commencement, and guidance on bond alternatives.
In UK construction, cash retention is a contractual practice of holding back a percentage of sums otherwise due, typically from interim or final payments, as security that the contractor or subcontractor will finish the work and put right defects during a defects or rectification period.
In plain English, part of the money already earned for labour and materials stays with the payer until release conditions are met. Release is often staged (part at practical completion, the balance after the defects period), but percentages, triggers and timing are contract-specific. This primer does not present market norms as statute.
Retention ties up working capital down the supply chain. Smaller firms may wait months or years for sums that relate to work already done, and insolvency higher in the chain can make recovery harder. Those cash-flow risks help explain why UK policymakers focused on the practice. This page explains the policy; it does not argue for or against it.
Retention is not a surety bond. A bond is a three-party guarantee (obligee, principal and surety). Cash retention is a withholding of contract cash. That distinction is the hinge of the Bill's retention measures and of the bond-alternative discussion below. For why owners ask for that three-party guarantee in the first place, see why obligees require bonds.
Cash retention holds back part of the sums already earned until release conditions are met.
What the Commercial Payments Bill does on retention
Exact Bill name and stage
The short title is the Commercial Payments Bill [HL], a Government Bill taken through the Lords for the Department for Business and Trade by Lord Leong. The long title includes provision "to ban retention clauses in the construction sector," alongside wider commercial-payment measures. If enacted in its current form, clause 33 says it "may be cited as the Commercial Payments Act 2026"; it is not an Act yet. Live tracker: bills.parliament.uk/bills/4128.
The GOV.UK overview (19 May 2026) summarises the construction measure as prohibiting the deduction and withholding of retention payments under a construction contract, and states that the Government will consult further on the timing for implementation. The measures are described as not applied retrospectively.
Stage
Date
Status
Lords First Reading
19 May 2026
Complete
Lords Second Reading
9 June 2026
Complete
Lords Committee
21 July 2026
Complete
Lords Report
15 September 2026
Complete
Lords Third Reading
20 October 2026
Complete: passed and sent to the Commons
House of Commons
First Reading 21 October 2026; Second Reading not yet scheduled (as of October 28 check)
In progress
Royal Assent
—
Still open
Status note: Text discussed here is HL Bill 55 (as amended on Report), the version the Lords sent to the Commons on 20 October 2026; the Lords made only a privilege amendment at Third Reading. The Commons print is Bill 166 (as brought from the House of Lords, 21 October 2026); check clause numbers against it.
Retention mechanism (HL Bill 55, clauses 12–17 and 32)
The Bill would amend Part 2 of the Housing Grants, Construction and Regeneration Act 1996 (HGCRA 1996) by inserting new sections 113A to 113F. Under the Bill as it left the Lords:
Clause 12 (new s.113A) describes the retention practice: one party deducting or retaining sums equating to a percentage of the amount payable, an interim payment or the contract total, until a release condition is met (for example, the end of a defects period). Under s.113B(1), a retention clause need not be in writing and may sit in the construction contract or in a "related agreement," which the Bill defines as "an agreement relating to sums payable under that contract."
Clause 13 (new s.113B) makes retention clauses agreed or varied during a transition period ineffective after a set day. Section 113B(10) defines both periods: "'the transition period' means the period of two years beginning with the day on which this section comes into force," and "'the last retention day' means the last day of the period of three years beginning with the day on which this section comes into force." Sums deducted during the transition period and still unpaid at the end of the last retention day become a "transitional retained sum" (s.113B(4)) and are treated under the HGCRA 1996 payment provisions (s.113B(5)). Their payment due date is "the last day of the period of 30 days beginning with the day after the last retention day," or "such earlier date (after the last retention day) as is agreed by the parties in writing" (s.113B(7)).
Clause 14 (new s.113C) bans retention clauses that the parties "agree after the end of the transition period." Such a clause "is void."
Clause 15 (new s.113D) voids variations of pre-existing retention clauses that the parties agree after the end of the transition period (s.113D(1)–(2)), but not a variation "that has the effect of making the retention clause or related term more favourable to the payee than it was before the variation" (s.113D(3)).
Clause 16 (new s.113E) implies a fixed sum where an unauthorised retention creates a "retention debt" after the transition period: "the higher of— (a) £40; (b) the sum that is 50% of the retention debt." This is in addition to statutory interest and late-payment compensation. The fixed sum "may be remitted in whole or part" if "the interests of justice require it" (s.113E(5)).
Clause 17 (new s.113F) lets the Secretary of State amend the core retention definitions by regulations, after consultation and subject to approval by both Houses (affirmative procedure).
Start date not set. Clause 32(1) leaves commencement to "such day as the Secretary of State may by regulations appoint," and clause 32(3) brings clauses 14, 15 and 16 into force "on the day after the last day of the period of two years beginning with the day on which sections 12 and 13 come into force". No commencement regulations have been made, so the two-year and three-year periods above have no calendar dates. They describe the Bill as it left the Lords, not settled law, and the Commons could change them.
Still open: the precise commencement date (commencement regulations under clause 32; GOV.UK: further consultation on timing). Trade-press estimates of an implementation year are not enacted law. The Bill also caps payment terms in commercial contracts at 30 days where the purchaser is a public authority and 60 days otherwise (new s.2B(2) CPILPA 1998), with a power to shorten them later. This primer stays on retention and bonds.
Why surety and bonds show up as alternatives
If statute removes cash withholding, owners still need a path to defects and completion security. At Lords Report on 15 September 2026, Lord Leong set out the Government's direction in Hansard:
Construction should move away from cash retentions and toward "modern, more secure and equitable forms of surety."
Alternatives named: performance bonds and retention bonds, "already available in the UK," and warranty bonds, described as "very common in Europe" and available in the UK.
"We will be working with surety providers to ensure that a range of alternatives is available when the ban comes into force." The minister added that "The Construction Leadership Council has now appointed a new industry lead for this area," with increased engagement from September 2026.
Escrow: ordinary payment through a bank or escrow provider remains permitted; money held by a third party as security for performance could itself amount to a retention. Genuine staged payments remain permissible, but relabelled withholding can still be a retention.
Those are ministerial statements about policy direction. They are not a finished exemption list, not surety ratings and not Global Guarantors product advice.
Instrument
Plain-English role
Caution
Performance bond
Surety supports the obligee if the bonded contractor defaults on performance (wording-specific).
UK forms differ from US and Canadian specimens; read the bond.
Retention bond
Lets cash retention be released while the obligee keeps recourse to a guarantor if defects or release conditions are not met.
Named by the minister as an alternative. Still open: how "related agreement" drafting treats retention bonds.
Warranty bond
Named in Hansard; market- and wording-specific.
Coverage scope depends on the wording.
Escrow as payment conduit
Permitted for making payment (ministerial clarification).
Holding cash as performance security may be treated as retention.
Release is often staged: part at practical completion, the balance after the defects period.
Global Guarantors does not publish premiums, capacity, AM Best ratings or UK market share. Whether an employer accepts a bond in place of cash retention after a ban is a contracting and underwriting question. If a bond is called, the claim process turns on its wording; see Surety claims basics.
What readers should watch next
House of Commons stages: First Reading took place on 21 October 2026. Second Reading, Committee, Report and Third Reading are still open. If the Commons amends the Bill, the Lords consider the changes.
Royal Assent: still open. It is not an Act as of October 28, 2026.
Commencement regulations and the Government's further consultation on retention-ban timing: still open.
Resident management company exemption: debated at Lords Report and not pressed; the Government opposed it. FIS (21 October 2026) expects it to be tabled again in the Commons.
Affirmative regulations, CLC guidance on alternative surety, and the "related agreement" versus bond question: still open.
Short North America orientation
This page is UK-focused. A brief bridge for US and Canadian readers:
US "retainage" and UK "retention" are related (contractual withholding for completion and defects leverage) but not identical regimes. US retainage is largely state- and contract-driven; Colorado, for example, now lets contractors on private projects tender a retainage bond in lieu of cash retainage. Miller Act and Little Miller Act bonds answer different questions than a UK cash-retention ban.
Canadian holdback under provincial prompt-payment rules is a distinct structure; see the Canada prompt payment guide in Related reading below. UK Bill clauses do not map onto Canadian holdback percentages.
For North American readers with UK projects, treat this as awareness. UK cash retention may be reshaped by statute, and bond and wording diligence (plus UK counsel) matter more than importing US retainage habits.
What to verify at the source
Stage: whether Commons Second Reading or later stages have happened since October 28, 2026 (see the Bill stages page linked in the box above).
Clause numbers: whether the Commons print, Bill 166, renumbers clauses 12–17 and 32 (Publications).
Commencement: whether commencement regulations or the Government's further consultation on timing have been published.
Bond alternatives: any CLC or Government guidance on retention bonds, warranty bonds and "related agreement" drafting.
Your contract: the retention clause, any related agreement and any bond wording on your own project, with UK counsel.
Guardrails
Not legal advice. The Bill text, Hansard and any commencement regulations control.
Not placement or underwriting advice. No premiums, capacity, ratings or "which bond to buy."
Not lobbying. Global Guarantors takes no position for or against the Bill on this page.
Moving target. Open items are labelled "Still open" on purpose.
Secondary sources are pointers only. Firm and trade articles are not the Bill.
Forms win. Rights turn on the issued wording and governing law.
Mills & Reeve: Third reading next (22 Sep 2026), written before Third Reading
Gateley: Retention ban implementation (27 May 2026): early drafting commentary; may predate Report clarifications
FIS: Payments Bill set to clear the Lords (21 Oct 2026): cited only for its expectation that the resident management company amendment returns in the Commons
Global Guarantors Education: educational content on a UK Bill still before Parliament. Not a summary of an Act. Not bonding, insurance or legal advice. Always verify Bill stage, text, commencement and market practice at primary sources.