A subcontractor sued on a federal payment bond about two years after its last day of work — twice the one-year limit — and lost. The same order freed one surety from a performance bond claim because no default was ever declared to it. Education only; not legal advice.
Published: October 8, 2026 · Last verified: October 8, 2026 (PT)
A federal court in Florida has thrown out a subcontractor’s Miller Act payment bond claim because the lawsuit came roughly two years after the subcontractor’s last day of work — double the one-year deadline in the statute. In the same order, one surety escaped a performance bond claim because the general contractor never declared the subcontractor in default to that surety before suing. Both lessons matter to anyone who relies on a construction bond: a bond only pays if the claimant follows its rules and deadlines.
Verify at source / not legal advice. This summary is based on the court’s public order dated August 27, 2026 and an October 6, 2026 commentary by construction lawyer David Adelstein. It is one district-court decision on its own facts. Confirm the docket and speak with counsel before relying on it for a live bond claim.
| Item | Detail |
|---|---|
| Case | Sauer Construction, LLC v. United Structures of Georgia, LLC, Western Surety Company and Great Midwest Insurance Company, No. 3:24-cv-943-WWB-PDB |
| Court | U.S. District Court for the Middle District of Florida (often shortened to “M.D. Fla.”), Jacksonville Division |
| Order date | August 27, 2026 (reported as 2026 WL 2522849) |
| Project | Renovation of Army barracks buildings 2273, 2387 and 2389 at Fort Johnson, Louisiana |
| General contractor | Sauer Construction, LLC |
| Subcontractor | United Structures of Georgia, LLC — furnish and install metal trusses and decking, under two subcontracts |
| Sureties | Federal Insurance Company — payment bonds on Sauer’s side under the Miller Act. Western Surety Company — payment and performance bonds for United Structures on the building 2273 subcontract. Great Midwest Insurance Company — payment and performance bonds for United Structures on the buildings 2387/2389 subcontract. |
| Dollar amounts in dispute | Not publicly disclosed in the order as of Oct 8, 2026 |
According to the order, the barracks projects “were plagued by delays,” and Sauer and United Structures argued over payments, change orders, site access, quality of work and schedules. United Structures eventually told Sauer it would do no more work on buildings 2387 and 2389. The parties agreed that United Structures’ last day of labor or materials was no later than September 9, 2022.
United Structures then submitted payment bond claims to Federal Insurance, the surety on Sauer’s federal payment bond. Federal Insurance told United Structures it had found a “bona fide dispute” about what, if anything, was owed, and invited more documentation. The court noted that United Structures kept pursuing the claim with the surety into May 2023. The lawsuit was not started until September 11, 2024.
The Miller Act is the federal law that requires prime contractors on most federal construction contracts to post a performance bond (protecting the government) and a payment bond (protecting subcontractors and suppliers who are not paid). Because a subcontractor cannot put a lien on federal property, the payment bond is usually its main safety net. That safety net comes with a hard time limit: a suit on the bond “must be brought no later than one year after the day on which the last of the labor was performed or material was supplied” (40 U.S.C. § 3133(b)(4)).
United Structures argued the deadline should be paused — “equitable tolling” — because the surety never issued a final, clear denial and kept the claim open. The court took a careful two-step approach:
Result: summary judgment for Sauer and Federal Insurance on the Miller Act counterclaim. The court also rejected United Structures’ backup unjust enrichment claim, explaining that a subcontractor’s remedy against a Miller Act surety runs through the bond itself, and that under Louisiana law unjust enrichment is not available where a contract already governs the relationship.

Sauer also sued the two sureties that had bonded United Structures’ work, Western Surety and Great Midwest, under their subcontract performance bonds. A performance bond is a promise by the surety to step in if the bonded contractor (the “principal”) fails to perform. The bonds here said the surety’s duties kick in “whenever the Principal shall be, and is declared by the Obligee to be in default,” and let Sauer fix the default itself only “after having given notice to the Surety.”
The court read that standard language as making a declaration of default a condition that must be met before suing the surety. Applying Louisiana case law, it explained that a declaration must be made “in clear, direct, and unequivocal language.” Filing the lawsuit did not count.
| Surety | What the record showed | Outcome |
|---|---|---|
| Western Surety (building 2273) | Western Surety testified it never received any written communication about United Structures’ performance. Sauer’s own witness did not believe notice had actually been given. | Summary judgment for the surety — performance bond claim fails |
| Great Midwest (buildings 2387/2389) | A January 31, 2023 “notice of default and backcharge” email was copied to a wrong address for Great Midwest. But Great Midwest opened a claim file in March 2023 and later held emails in which Sauer said it would file a claim with the surety. | Surety’s motion denied — a jury could find notice was enough, so the claim goes forward |
The difference between the two sureties came down to paperwork that reached the right desk. Sending a default notice to a wrong email address is a small mistake that can become a very expensive one.
For readers who handle federal jobs, here is how the main deadlines work under 40 U.S.C. § 3133. Your clock starts on your own last day of labor or materials on the project, not the end of the whole job.
Two more points from the statute: you can ask the contracting agency for a certified copy of the payment bond by submitting an affidavit that you supplied labor or material and have not been paid (§ 3133(a)), and a waiver of your right to sue on the bond is void unless it is in writing, signed by you, and signed after you furnished the labor or material (§ 3133(c)). The statute requires these bonds on federal construction contracts “of more than $100,000” (40 U.S.C. § 3131(b)); the Federal Acquisition Regulation sets the working threshold contracting officers apply, so check the current figure there.
The order resolved the Miller Act, unjust enrichment, fraud and attorney’s-fees counterclaims in Sauer’s and Federal Insurance’s favour, and the performance bond claim against Western Surety. The performance bond claim against Great Midwest and the contract dispute between Sauer and United Structures remain. Whether any party has appealed or settled is not publicly disclosed as of Oct 8, 2026.
Verify at source / not legal advice. Dates, parties and holdings track the public court order and statute text as of October 8, 2026 (PT). Deadlines can turn on facts and contract terms — confirm with counsel before relying on this summary. Questions or corrections: [email protected].