Consent of surety after award: FAR 28.106-3 and 28.106-5, SF 1414 and SF 1415, SF 25 notice waiver, when consent is not required, and a Canada contrast.
Education only / verify at source / not legal advice. This guide explains consent of surety after a construction contract is awarded, using the Federal Acquisition Regulation (FAR), GSA Standard Forms and related public sources. Global Guarantors publishes industry education. We aren't a surety, broker, insurer or law firm, and we don't publish premiums. The bond wording, the contract, the governing law and your own lawyer's advice control.
Start here: Contract surety hub · Surety glossary · Surety 101: three parties, one written promise
A performance bond and a payment bond are written against a contract. The contract then changes: a change order adds scope, the price swings, the schedule slips, or the contractor’s legal entity is novated to a successor. Owners and contracting officers often ask a simple question next: does the surety still stand behind the bond as modified?
In US federal practice that question has a name and two standard forms. The FAR defines consent of surety as “an acknowledgment by a surety that its bond given in connection with a contract continues to apply to the contract as modified” (FAR 28.001). Agencies use Standard Form 1414 when the penal sum stays the same and Standard Form 1415 when the original surety also increases the penalty. Neither form is a new bond, a dual-obligee rider, or a tender-stage “agreement to bond.” Each is a written acknowledgment that the existing bond covers the contract as changed.
This guide stays US-priority and federal-first. It maps FAR 28.106-3 and 28.106-5, the SF 1414 / SF 1415 wording, how those forms sit beside the SF 25 performance bond’s notice-waiver language, when consent is not required, and what silence can mean when the form and the FAR diverge. A short Canada section contrasts tender-stage consent of surety with the federal post-award instrument. State and municipal owners often borrow the idea without using the federal forms; those programs vary, so they sit under What to verify.
Start with the federal definition, because it is short and careful. FAR 28.001 says:
Consent of surety means an acknowledgment by a surety that its bond given in connection with a contract continues to apply to the contract as modified.
Four things follow from that sentence.
It is an acknowledgment, not a new bond. The surety is saying the bond already delivered still answers for the contract as changed. When the government needs more coverage from the original surety, FAR 28.106-3(a) points agencies to SF 1415, which both consents and increases the penalty. When the extra coverage comes from a new surety (or from a 28.204 alternative), 28.106-3(b) points to a new SF 25, SF 25A, SF 1418 or SF 1416, not to SF 1415 alone.
It is not a rider in the commercial-surety sense. Licence, customs and freight bonds often change by rider: a named change, an address change, or an increase recorded on a rider form under a statute such as 19 CFR 113.24. Contract surety uses different paper. On federal construction work the post-award paper is SF 1414 or SF 1415 (FAR 28.106-1(k)–(l)). Calling every change a “rider” blurs that distinction.
It is not a dual-obligee endorsement. A dual-obligee rider adds a second named obligee (for example a lender) to an existing bond. Consent of surety under FAR 28.001 is about the contract as modified, not about adding obligees. Dual-obligee practice is outside this guide’s primary sources; treat it as a separate underwriting and wording question.
It is not a tender-stage agreement to bond. In Canada, and on some US private and state jobs, owners ask for a surety letter with the bid promising to issue the final bonds if the bidder wins. Federal sealed bidding does not treat that letter as a substitute for a required bid guarantee. The federal consent forms are used after award, on a modification. Our glossary entry on consent of surety makes the same “read the specimen” point in one paragraph; this page is the long form.
It is not a release, waiver, final-payment certificate or retainage release. Consent under FAR 28.001 acknowledges that an existing bond continues to apply to the contract as modified. It does not, by itself, discharge the surety, waive claims, certify final payment or release retainage. Keep those instruments and milestones separate from SF 1414 / SF 1415.
| Instrument and federal form | Timing | What it does |
|---|---|---|
| Bid guarantee / bid bond (SF 24) | With the bid | Assures the bidder will sign and furnish final bonds |
| Performance / payment bond (SF 25 / SF 25A) | At award | Secures performance and payment on the awarded contract |
| Consent of surety (SF 1414) | After award, on a modification | Acknowledges the existing bond covers the contract as modified |
| Consent + increase of penalty (SF 1415) | After award, when original surety increases coverage | Consent plus higher performance and/or payment penalty |
| New bond from a new surety (SF 25 / SF 25A, or 1418 / 1416) | When additional coverage is not from the original surety | Fresh bond(s), not a consent form alone |
| Tender-stage “consent” / agreement to bond (no CCDC standard; not SF 1414) | With the bid (often Canada) | Surety’s commitment to issue final bonds if awarded |
Bonded work is dynamic. Change orders, constructive changes, time extensions, deductive credits and novations are ordinary project tools. From the obligee’s seat, three risks sit behind the request for consent.
Scope risk. A bond written on a $10 million road package is not automatically the same promise when the package grows into a $16 million package with a new interchange. FAR 28.106-5 treats “new work beyond the scope of the original contract” as a consent trigger even when no additional bond is required.
Price-swing risk. The same section treats a same-scope price change of more than 25 percent or $50,000—upward or downward—as a consent trigger when no additional bond is required. Downward changes matter because the surety’s exposure profile and the contractor’s remaining work both move.
Party risk. A novation replaces the contractor of record. FAR 28.106-5(a)(3) says consent of surety is required for a novation agreement (see subpart 42.12). FAR 42.1203’s processing checklist also calls for the consent of sureties on listed contracts when bonds are required, or a statement that none are required; it does not itself name SF 1414. SF 1414 is the form FAR 28.106-5(c) tells agencies to use for consent of surety.
General contractors ask for consent for a related reason: they need the change order package to clear the owner’s contracting officer, the lender’s checklist, or the public owner’s bond desk. Our public owner guide to accepting and verifying bonds already summarizes the federal consent paragraph; this page is the deep dive that sits beside that checklist.
On Miller Act federal construction, performance and payment bonds exist because the statute and FAR 28.102 require them above the applicable thresholds. Consent questions usually arise only after those bonds are in place. The Miller Act and little Miller Act guide covers when the bonds are required; it does not need to be repeated here.
FAR 28.106-5(a) is the operational rule. When any contract is modified, the contracting officer shall obtain the consent of surety if:
FAR 28.106-5(c) then says agencies shall use Standard Form 1414, Consent of Surety, for all types of contracts.
FAR 28.106-3 separates who supplies the extra coverage:
FAR 28.106-1 lists the forms in one place: SF 1414 (see 28.106-5) and SF 1415 (see 28.106-3).
GSA’s current Consent of Surety form is STANDARD FORM 1414 (REV. 10/2023), prescribed by GSA-FAR (48 CFR) 53.228(k). The operative sentence is:
The Surety (Co-Sureties) consents (consent) to the foregoing contract modification and agrees (agree) that its (their) bond or bonds shall apply and extend to the contract as modified or amended.
The form carries the contract number, modification number and date, and signature blocks for the individual or corporate principal and for each corporate or individual surety (with co-surety blocks A–C and a continuation). The instructions on the form say the principal or authorized representative shall execute the consent with the modification to which it pertains, and that a power of attorney or certificate of corporate principal must accompany the consent when the signer is not a partner, joint venturer or corporate officer.
STANDARD FORM 1415 (REV. 10/2023), prescribed by 53.228(l), repeats the consent sentence and then adds the increase:
The Principal and Surety (Co-Sureties) further agree that on or after the execution of this consent, the penalty of the performance bond or bonds is increased by … dollars and the penalty of the payment bond or bonds is increased by … dollars. However, the increase of the liability of each Co-Surety resulting from this consent shall not exceed the sums shown below.
Blocks then list each surety’s increase in liability limit under the performance bond and under the payment bond. That co-surety ceiling language matters on large packages where several companies share the bond.
FAR 28.106-2 covers substitution of surety bonds: a new surety bond covering all or part of the obligations on a previously approved bond may be substituted if approved by the head of the contracting activity (or as agency regulation provides). When a new bond is approved, the contracting officer notifies the principal and surety of the original bond of the new bond’s effective date. Substitution is not the same paperwork as SF 1414 consent on a routine change order.
FAR 28.106-4(a) tells the contracting officer to insert 52.228-2, Additional Bond Security, in solicitations and contracts when bonds are required. The clause (Oct 1997) requires the contractor to furnish additional security if, among other things, “the contract price is increased so that the penal sum of any bond becomes inadequate in the opinion of the Contracting Officer.” That clause is about getting more security; SF 1415 is the form when the original surety supplies the increase.
The federal SF 25 performance bond (REV. 10/2023) is the bond most federal construction consent questions sit on. Its void condition says the obligation is void if the principal:
(a)(1) Performs and fulfills all the undertakings, covenants, terms, conditions, and agreements of the contract during the original term of the contract and any extensions thereof that are granted by the Government, with or without notice of the Surety(ies) and during the life of any guaranty required under the contract, and
(2) Performs and fulfills all the undertakings, covenants, terms, conditions, and agreements of any and all duly authorized modifications of the contract that hereafter are made. Notice of those modifications to the Surety(ies) are waived.
Two educational points follow, and neither one invents a default lawsuit outcome.
The bond anticipates modifications. SF 25’s own condition reaches “duly authorized modifications” and extensions “with or without notice.” That is why many routine change orders never produce a separate surety signature on private forms that copy this idea.
The FAR still lists consent triggers. FAR 28.106-5 tells the contracting officer to obtain SF 1414 in the cases it names. The notice waiver on SF 25 does not delete 28.106-5. Treat the bond wording and the regulation as two layers: the bond says the surety need not receive notice of duly authorized modifications for the void condition to reach them; the FAR still tells the agency when to collect a consent form. Whether a particular modification is “duly authorized,” and what happens if the agency skips a required SF 1414, are fact- and counsel-specific questions listed under What to verify.
FAR 28.106-5(b) is as important as 28.106-5(a):
When a contract for which performance or payment is secured by any of the types of security listed in 28.204 is modified as described in paragraph (a) of this subsection, no consent of surety is required.
FAR 28.204 lets a person required to furnish a bond furnish the types of security in 28.204-1 through 28.204-3 instead of a corporate or individual surety. The contractor still executes the bond forms as principal; the security is pledged in lieu of a surety signature. Because there is no surety on those instruments, the consent-of-surety step drops out for the modifications described in 28.106-5(a).
Other practical “not required” readings stay inside the text:
Do not read 28.106-5(b) as a license to skip consent whenever an irrevocable letter of credit sits beside a corporate surety bond. Paragraph (b) reaches contracts “secured by any of the types of security listed in 28.204.” FAR 28.204 also allows combinations of those securities with surety bonds, so a mixed package needs a source-level read of what actually secures performance or payment before treating consent as off.
The table below is a teaching map for federal work. It is not a decision tree for every agency supplement, and it does not decide private-owner practice.
| Situation | FAR / form cue | Typical paper |
|---|---|---|
| Same-scope change order; price move ≤25% and ≤$50,000; no additional bond | Outside 28.106-5(a)(2)(ii) as written | Often no SF 1414; SF 25 notice waiver still in the bond |
| Same-scope change order; price move >25% or >$50,000; no additional bond | 28.106-5(a)(2)(ii) | SF 1414 |
| Modification for new work beyond original scope; no additional bond | 28.106-5(a)(2)(i) | SF 1414 |
| Additional coverage from the original surety | 28.106-3(a) | SF 1415 (consent + increase) |
| Additional coverage from a new surety | 28.106-3(b); 28.106-5(a)(1) | New SF 25 / SF 25A (and SF 1414 per (a)(1) as the regulation requires) |
| Additional coverage via 28.204 alternative | 28.106-3(b); 28.106-5(b) | New or adjusted 28.204 security; no consent of surety under (b) |
| Time extension only, no price or scope change described in 28.106-5(a)(2) | Not named as its own trigger in 28.106-5(a)(2) | SF 25 already reaches extensions “with or without notice”; confirm agency policy |
| Novation / successor in interest | 28.106-5(a)(3) and (c); 42.1203 surety-consent document; subpart 42.12 | SF 1414 with the novation agreement package |
| Substitution of the bond / surety | 28.106-2 | New bond approved by head of contracting activity; notice to original principal and surety |
| Penal sum inadequate after a price increase | 52.228-2(c) | Additional security; SF 1415 if original surety increases |
Time extensions. SF 25’s void condition expressly reaches extensions granted by the government “with or without notice of the Surety(ies).” FAR 28.106-5 does not list “time only” as a separate consent trigger. Many projects still send the surety a courtesy notice or an agency-required letter. Courtesy is not the same as SF 1414; check the contract and the agency’s bond desk rules.
Deductive changes. FAR 28.106-5(a)(2)(ii) counts price changes “upward or downward.” A large credit that cuts the contract price by more than 25 percent or $50,000 sits inside that text when no additional bond is required.
Co-surety and megaproject packages. When several sureties share one bond, SF 1415’s per-surety increase limits matter. Capacity assembly and co-surety structure are covered on our megaproject and co-surety education pages; the consent form is only the modification paper.
If the project later moves from a modification dispute into a default, the questions shift from consent to takeover, tender and claim handling. That path is covered in surety obligations after a performance bond default.
Readers often want a single default rule: “if the surety stayed silent, the change is covered” or “if SF 1414 is missing, the bond is void.” Public primary sources do not hand out either slogan.
On SF 25 federal performance bonds, the form already says duly authorized modifications are inside the void condition and that notice is waived. Silence after a routine, duly authorized change order is therefore not, by itself, proof that the bond dropped the modification. It is also not proof that the contracting officer was free to skip SF 1414 when 28.106-5 required it.
Where the bond form is not SF 25, the answer starts with the specimen. Some private and AIA-style forms require surety consent for material alterations; some do not. Some make coverage of extras conditional on consent; some treat consent as an owner protection without spelling out the consequence of omission. The glossary’s one-line warning applies: whether consent is required, and what silence means, depends on the bond wording, the contract and the surety’s instructions.
Where the FAR required SF 1414 and the file does not have it, the gap is an agency file-compliance and claims question for counsel and the parties. This guide does not invent a discharge, a coverage default or another remedy. Put the modification, the bond edition and the FAR text in front of counsel.
Where the surety is asked for consent and declines, the practical project outcomes vary: the owner may refuse the change order, the parties may reshape the modification, the contractor may need a new bond under 28.106-3(b), or the parties may renegotiate. None of those outcomes is prescribed as a single FAR default in the sections reviewed for this page.
Canadian public tenders often use the words “consent of surety” for a tender-stage instrument. The Surety Association of Canada describes three common pre-tender or tender tools: a non-binding pre-qualification letter, a consent of surety (agreement to bond), and the bid bond itself. The consent of surety in that setting is signed by the surety and commits the surety to issue the final performance and payment bonds if the bidder is awarded and signs the contract. It does not, on the SAC framing used on our Canada bid-bonds page, assure that the contractor will enter into the contract at the quoted price. There is no CCDC standard consent-of-surety form; CCDC 220 – 2024 is the bid bond, and CCDC 221 / 222 are the final performance and labour-and-material payment bonds.
That Canadian tender instrument is not FAR SF 1414. The federal US forms acknowledge that an already issued bond continues to apply to a modified contract. The Canadian tender consent is about willingness to issue final bonds after award.
Post-award change-order consent practice in Canada is wording- and owner-specific. Licensed CCDC specimens are not reproduced here. For field orientation, see the live wording cards for CCDC 221 – 2024 performance and the education page on bid bonds in Canada and CCDC 220 tendering. Read the actual bond and the change-order clause before treating any Canadian project as “FAR-like.”
| US federal post-award consent | Canadian tender-stage consent (typical SAC framing) | |
|---|---|---|
| When | After award, on a modification | With the bid / at award condition |
| Core promise | Existing bond continues to apply to the contract as modified | Surety will issue final bonds if the bidder is awarded and signs |
| Standard form | SF 1414 / SF 1415 (REV. 10/2023) | No CCDC standard consent form |
| Signed by | Surety (and principal on the federal forms) | Surety (agreement to bond); bid bond separately signed by principal and surety |
General education, not legal advice. Use it as a list of questions for the contracting officer, the obligee’s bond desk, your surety professional and your lawyer.
Before the modification is signed
When consent or an increase is needed
After the file is assembled
What is consent of surety? Under FAR 28.001 it is an acknowledgment by a surety that its bond given in connection with a contract continues to apply to the contract as modified. On federal work the usual forms are SF 1414 (consent) and SF 1415 (consent plus increase of penalty).
Is consent of surety the same as a change-order rider? Not on federal construction. FAR Part 28 points to SF 1414 / SF 1415 for post-award consent and increase. Licence and customs bonds often use statutory riders instead. Read the specimen for the bond you have.
When does the FAR require SF 1414? When a contract is modified and one of the FAR 28.106-5(a) triggers applies: an additional bond from other than the original surety; new work beyond the original scope with no additional bond; a same-scope price change of more than 25 percent or $50,000 with no additional bond; or a novation agreement under subpart 42.12.
When is consent of surety not required? FAR 28.106-5(b) says no consent of surety is required when performance or payment is secured by any of the types of security listed in 28.204 and the contract is modified as described in 28.106-5(a). Same-scope price moves that stay at or under both the 25 percent and $50,000 marks also sit outside 28.106-5(a)(2)(ii) as written.
Does SF 25’s notice waiver mean I never need consent? No. SF 25 waives notice of duly authorized modifications for purposes of its void condition. FAR 28.106-5 still tells the contracting officer when to obtain SF 1414. Read both.
Is a Canadian “consent of surety” the same thing? Usually not. On many Canadian tenders the phrase means a surety’s agreement to issue the final bonds if the bidder is awarded and signs. That is a tender-stage instrument, not FAR SF 1414 / SF 1415.
Retrieved November 6, 2026 (PT); selected FAR and GSA sources re-checked the same day for the Advisor spot-check.